Construction of EWS Houses (G+3 Floor) under PM AVAS YOJNA, at KANKAHA, MOHANLALGANJ, LUCKNOW (PHASE-2).

by U.P. Awas Evam Vikas Parishad

Lucknow, Uttar Pradesh · UPRERAPRJ398030

Registered

Total units

720

Overview

Registration Date2020-07-14
RERA NumberUPRERAPRJ398030
Promoter IDUPRERAPRM4243
Proposed Start2021-07-01
Proposed Completion2025-06-30

Location

DistrictLucknow
TehsilMohanlalganj
StateUttar Pradesh
Map unavailable — no coordinates on file.

Land Details

Project TypeNew
Total Units720
Unit Types1
Blocks15
Floors4

Khasra records (2)

  • 194· Khasra· 8980
  • 195· Khasra· 35790

Inventory

Apartments (60 rows)
BlockFloorTypeCountCarpet (m²)BalconyGarage
1GF1 BHK1222.770
111 BHK1222.7712
121 BHK1222.7712
131 BHK1222.7712
2GF1 BHK1222.770
211 BHK1222.7712
221 BHK1222.7712
231 BHK1222.7712
3GF1 BHK1222.770
311 BHK1222.7712
321 BHK1222.7712
331 BHK1222.7712
4GF1 BHK1222.770
411 BHK1222.7712
421 BHK1222.7712
431 BHK1222.7712
5GF1 BHK1222.770
511 BHK1222.7712
521 BHK1222.7712
531 BHK1222.7712
6GF1 BHK1222.770
611 BHK1222.7712
621 BHK1222.7712
631 BHK1222.7712
7GF1 BHK1222.770
711 BHK1222.7712
721 BHK1222.7712
731 BHK1222.7712
8GF1 BHK1222.770
811 BHK1222.7712
821 BHK1222.7712
831 BHK1222.7712
9GF1 BHK1222.770
911 BHK1222.7712
921 BHK1222.7712
931 BHK1222.7712
10GF1 BHK1222.770
1011 BHK1222.7712
1021 BHK1222.7712
1031 BHK1222.7712
11GF1 BHK1222.770
1111 BHK1222.7712
1121 BHK1222.7712
1131 BHK1222.7712
12GF1 BHK1222.770
1211 BHK1222.7712
1221 BHK1222.7712
1231 BHK1222.7712
13GF1 BHK1222.770
1311 BHK1222.7712
1321 BHK1222.7712
1331 BHK1222.7712
14GF1 BHK1222.770
1411 BHK1222.7712
1421 BHK1222.7712
1431 BHK1222.7712
15GF1 BHK1222.770
1511 BHK1222.7712
1521 BHK1222.7712
1531 BHK1222.7712

Permits & Approvals

Permit NoUPHDB/APD/UN-4/PMAY/CD-11/KANKAHA/189/2018
Permit Date2020-06-09
Valid Until2025-12-31
Extendable Until2028-12-31

Documents

Filing documents

  • Details of Encumbrances
  • Details of Encumbrances
  • Commencement Certificate
  • Other Plan(If Any)
  • Proforma of Application Form
  • Proforma of Allotment Letter
  • Proforma of Conveyance Deed
  • Proforma of Conveyance Deed
  • Proforma of Conveyance Deed
  • Proforma of Completion Certificate(Occupancy)
  • Waste Disposal Plan
  • Water Supply Plan
  • Water Supply Plan
  • Electricity Supply Plan
  • Electricity Supply Plan
  • Development Work Plan
  • Development Work Plan
  • Affidavit (Form-B)
  • Affidavit (Form-B)
  • CA CERTIFICATE
  • CA CERTIFICATE
  • ARCHITECT CERTIFICATE
  • ARCHITECT CERTIFICATE
  • ENGINEERS CERTIFICATE
  • ENGINEERS CERTIFICATE
  • Details of Encumbrances#New(2020-07-02)
    View
  • Commencement Certificate#New(2020-07-02)
    View
  • Other Plan(If Any)#New(2020-07-02)
    View
  • Proforma of Application Form#New(2020-07-02)
    View
  • Proforma of Allotment Letter#New(2020-07-02)
    View
  • Proforma of Conveyance Deed#New(2020-07-02)
    View
  • Proforma of Completion Certificate(Occupancy)#New(2020-07-02)
    View
  • Waste Disposal Plan#New(2020-07-02)
    View
  • Water Supply Plan#New(2020-07-02)
    View
  • Electricity Supply Plan#New(2020-07-02)
    View
  • Development Work Plan#New(2020-07-02)
    View
  • Affidavit (Form-B)#New(2020-07-02)
    View
  • CA CERTIFICATE#New(2020-07-02)
    View
  • ARCHITECT CERTIFICATE#New(2020-07-02)
    View
  • ENGINEERS CERTIFICATE#New(2020-07-02)
    View

Land documents

  • Extract of Khatauni#1421-1426(1900-01-01)
    770916684Khatauni Kankaha 194, 195.pdf
    View

Project Team

Architect AddressARCHITECT AND PLANNING UNIT-4, UPAVP, LUCKNOW
Engineer AddressPROF. DEPT. OF CIVIL ENGINEERING INSTITUTE OF ENGINEERING AND TECHNOLOGY LUCKNOW 226002

Developer & Contact

Developer

Promoter NameU.P. Awas Evam Vikas Parishad
Promoter Address104 Mahatma Gandhi Marg, Lucknow
Company TypeCompetent authority
Mobile8189081725
Emailupavp-rera@upavp.com
Registered Address104 Mahatma Gandhi Marg, Lucknow
Contractor Address104, MAHATMA GANDHI MARG, LUCKNOW

Development & Facilities

Development works

Demarcation Of PlotsAS PER SANCTION LAYOUT PLAN DEMARCATION OF PLOTS WILL BE DONE BEFORE EXECUTION
Boundary WallNO BOUNDARY WALL AS PER SANCTION LAYOUT PLAN
Road WorkYES AS PER ENCLOSED LAYOUT PLAN INTERNAL ROAD WILL BE CONSTRUCTED BY UPAVP AS PER NORMS APPROVED AND TRUNK ROAD WILL CONSTRUCTED BY UPPWD AS PER GO.-1878/AATH-1-16-80/MISCELLANEOUS/2010 DATE-17.10.2018
FootpathsNO FOOTPATHS REQURIED ON INTERNAL ROAD
Water Supply Including Drinking Water FacilitiesYES INTERNAL DRINKING WATER WATER LINE WILL BE EXECUTED BY UPAVP AS PER SANCTIONED DESIGN AND EXTERNAL WATER LINE WILL BE EXECUTED BY UP JAL NIGAM, LUCKNOW AS PER GO NO.-1878/AATH-1-16-80/MISCELLANEOUS/2010 DATE-17.10.2018
Sewer SystemYES AS PER SANCTIONED DESIGN SEWAGE SYSTEM WILL BE LAID BY UPAVP AND EXTERNAL SEWER LINE WILL BE LAID BY UP JAL NIGAM, LUCKNOW AS PER GO NO.-1878/AATH-1-16-80/MISCELLANEOUS/2010 DATE-17.10.2018
DrainYES AS PER SANCTIONED DESIGN OPEN BRICK DRAIN WILL BE CONSTRUCTED BY UPAVP AND EXTERNAL DRAIN WILL BE CONSTRUCTED BY UP JAL NIGAM, LUCKNOW AS PER GO NO.-1878/AATH-1-16-80/MISCELLANEOUS/2010 DATE-17.10.2018
ParksYES AS PER SANCTION LAYOUT PLAN PARKS WILL BE DEVELOPED BY PARISHAD ALSO PLANTATION.
Tree PlantingYES AS PER SANCTION LAYOUT PLAN TREE PLANTATION WORK OF SELECTED VARIETIES.
Design For Electric Supply Including Street LightingYES INTERNAL ELECTRIC SUPPLY WILL BE PROVIDED AS PER PARISHAD NORMS AND EXTERNAL ELECTRIC SUPPLY WILL BE PROVIDED BY UPPCL, LUCKNOW AS PER GO NO.-1878/AATH-1-16-80/MISCELLANEOUS/2010 DATE-17.10.2018
Community BuildingsCOMMUNITY BUILDING LIKE HEALTH CENTER, SCHOOLS, ANGANBARIES ETC. WILL BE DONE BY CONCERNING DEPARTMENT AS PER G.O.-1878/AATH-1-16-80/MISCELLANEOUS/2010 DATE-17.10.2018
Treatment And Disposal System Of Sewage And Sullage WaterYES FOR SEWAGE DISPOSAL INTERNAL SEWER LINE WILL BE CONSTRUCTED AS PER APPROVED LAYOUT AND EXTERNAL WILL BE DONE BY UP JAL NIGAM, LUCKNOW AS PER G.O.-1878/AATH-1-16-80/MISCELLANEOUS/2010 DATE-17.10.2018
Solid Waste Management And Disposal SystemWILL BE DONE BY UP JAL NIGAM, LUCKNOW AS PER G.O.-1878/AATH-1-16-80/MISCELLANEOUS/2010 DATE-17.10.2018
Water Conservation SystemYET TO BE PLANNED
Energy Management System Including Use Of Renewable EnergyYET TO BE PLANNED
Fire Protection And Fire Safety SystemNO FIRE PROTECTION AND FIRE SYSTEM REQUIRED IN BUILDING WITH HEIGHT LESS THAN 15 MTR
Social Infrastructure And Other Public Amenities Including Public Health ServicesYES IN SANCTION LAYOUT PLAN COMMERCIAL POCKET ARE PROVIDED
Emergency Evacuation ServicesNOT REQUIRED IN BUILDING WITH HEIGHT LESS THAN 15 MTR
Other Miscellaneous WorkYES WILL BE DONE AS PER SANCTION LAYOUT PLAN

Financials

Registration Fee (₹)19500
Project Duration (months)60