DPS PALLADIO

by BP Infra India LLP

Lucknow, Uttar Pradesh · UPRERAPRJ717338/01/2025

Registered

Total units

309

Overview

Registration Date2025-01-25
RERA NumberUPRERAPRJ717338/01/2025
Promoter IDUPRERAPRM331596
Proposed Start2024-11-05
Proposed Completion2029-11-04

Location

DistrictLucknow
TehsilMohanlalganj
VillageMASTEMAU
AddressPINTAIL PARK CITY - PHASE 3
StateUttar Pradesh
Map unavailable — no coordinates on file.

Land Details

Project TypeNew
Total Units309
Unit Types4
Blocks4
Floors15

Khasra records (1)

  • GH 4 Pintail Park City· Plot· 1096671

Inventory

Apartments (154 rows)
BlockFloorTypeCountCarpet (m²)BalconyGarage
TOWER - C92 BHK180.973
TOWER - C92 BHK280.963
TOWER - C93 BHK391.353
TOWER - C102 BHK180.973
TOWER - C102 BHK280.963
TOWER - C103 BHK391.353
TOWER - C112 BHK180.973
TOWER - C112 BHK280.963
TOWER - C113 BHK391.353
TOWER - C122 BHK180.973
TOWER - C122 BHK280.963
TOWER - C123 BHK391.353
TOWER - C132 BHK180.973
TOWER - C132 BHK280.963
TOWER - C133 BHK391.353
TOWER - C142 BHK180.973
TOWER - C142 BHK280.963
TOWER - C143 BHK391.353
TOWER - D12 BHK380.963
TOWER - D13 BHK391.523
TOWER - D22 BHK381.353
TOWER - D23 BHK392.123
TOWER - D32 BHK381.353
TOWER - D33 BHK392.123
TOWER - D42 BHK381.353
TOWER - D43 BHK392.123
TOWER - D52 BHK381.353
TOWER - D53 BHK392.123
TOWER - D62 BHK381.353
TOWER - D63 BHK392.123
TOWER - D72 BHK381.353
TOWER - D73 BHK392.123
TOWER - D82 BHK381.353
TOWER - D83 BHK392.123
TOWER - D92 BHK381.353
TOWER - D93 BHK392.123
TOWER - D102 BHK381.353
TOWER - D103 BHK392.123
TOWER - D112 BHK381.353
TOWER - D113 BHK392.123
TOWER - D122 BHK381.353
TOWER - D123 BHK392.123
TOWER - D132 BHK381.353
TOWER - D133 BHK392.123
TOWER - A13 BHK1103.714
TOWER - A13 BHK1103.74
TOWER - A24 BHK2120.265
TOWER - A23 BHK1103.714
TOWER - A23 BHK1103.74
TOWER - A34 BHK2120.265
TOWER - A33 BHK1103.714
TOWER - A33 BHK1103.74
TOWER - A44 BHK2120.265
TOWER - A43 BHK1103.714
TOWER - A43 BHK1103.74
TOWER - A54 BHK2120.265
TOWER - A53 BHK1103.714
TOWER - A53 BHK1103.74
TOWER - A64 BHK2120.265
TOWER - A63 BHK1103.714
TOWER - A63 BHK1103.74
TOWER - A74 BHK2120.265
TOWER - A73 BHK1103.714
TOWER - A73 BHK1103.74
TOWER - A84 BHK2120.265
TOWER - A83 BHK1103.714
TOWER - A83 BHK1103.74
TOWER - A94 BHK2120.265
TOWER - A93 BHK1103.714
TOWER - A93 BHK1103.74
TOWER - A104 BHK2120.265
TOWER - A103 BHK1103.714
TOWER - A103 BHK1103.74
TOWER - A114 BHK2120.265
TOWER - A113 BHK1103.714
TOWER - A113 BHK1103.74
TOWER - A124 BHK2120.265
TOWER - A123 BHK1103.714
TOWER - A123 BHK1103.74
TOWER - A134 BHK2120.265
TOWER - A133 BHK1103.714
TOWER - A133 BHK1103.74
TOWER - A144 BHK2120.265
TOWER - A143 BHK1103.714
TOWER - A143 BHK1103.74
TOWER - BGFSHOP1135.730
TOWER - B13 BHK491.533
TOWER - B13 BHK191.943
TOWER - B13 BHK191.933
TOWER - B23 BHK491.533
TOWER - B23 BHK191.943
TOWER - B23 BHK191.933
TOWER - B33 BHK491.533
TOWER - B33 BHK191.943
TOWER - B33 BHK191.933
TOWER - B43 BHK491.533
TOWER - B43 BHK191.943
TOWER - B43 BHK191.933
TOWER - B53 BHK491.533
TOWER - A14 BHK2120.265
TOWER - B53 BHK191.943
TOWER - B53 BHK191.933
TOWER - B63 BHK491.533
TOWER - B63 BHK191.943
TOWER - B63 BHK191.933
TOWER - B73 BHK491.533
TOWER - B73 BHK191.943
TOWER - B73 BHK191.933
TOWER - B83 BHK491.533
TOWER - B83 BHK191.943
TOWER - B83 BHK191.933
TOWER - B93 BHK491.533
TOWER - B93 BHK191.943
TOWER - B93 BHK191.933
TOWER - B103 BHK491.533
TOWER - B103 BHK191.943
TOWER - B103 BHK191.933
TOWER - B113 BHK491.533
TOWER - B113 BHK191.943
TOWER - B113 BHK191.933
TOWER - B123 BHK491.533
TOWER - B123 BHK191.943
TOWER - B123 BHK191.933
TOWER - B133 BHK491.533
TOWER - B133 BHK191.943
TOWER - B133 BHK191.933
TOWER - B143 BHK491.533
TOWER - B143 BHK191.943
TOWER - B143 BHK191.933
TOWER - C12 BHK380.963
TOWER - C13 BHK391.523
TOWER - C22 BHK180.973
TOWER - C22 BHK280.963
TOWER - C23 BHK391.353
TOWER - C32 BHK180.973
TOWER - C32 BHK280.963
TOWER - C33 BHK391.353
TOWER - C42 BHK180.973
TOWER - C42 BHK280.963
TOWER - C43 BHK391.353
TOWER - C52 BHK180.973
TOWER - C52 BHK280.963
TOWER - C53 BHK391.353
TOWER - C62 BHK180.973
TOWER - C62 BHK280.963
TOWER - C63 BHK391.353
TOWER - C72 BHK180.973
TOWER - C72 BHK280.963
TOWER - C73 BHK391.353
TOWER - C82 BHK180.973
TOWER - C82 BHK280.963
TOWER - C83 BHK391.353
TOWER - D142 BHK381.353
TOWER - D143 BHK392.123

Permits & Approvals

Permit NoGroup Housing/13035/LDA/BP/24-25/1625/22082024
Permit Date2024-11-05
Valid Until2029-11-04
Extendable Until2032-11-04

Documents

Filing documents

  • Details of Encumbrances
  • Other Plan(If Any)
  • Proforma of Completion Certificate(Occupancy)
  • Details of Encumbrances#New(2024-11-26)
    View
  • Commencement Certificate#New(2024-11-26)
    View
  • Proforma of Application Form#New(2024-11-29)
    View
  • Proforma of Allotment Letter#New(2024-11-29)
    View
  • Proforma of Conveyance Deed#New(2024-11-26)
    View
  • Waste Disposal Plan#New(2024-11-26)
    View
  • Water Supply Plan#New(2024-11-26)
    View
  • Electricity Supply Plan#New(2024-11-26)
    View
  • Development Work Plan#New(2024-11-26)
    View
  • Affidavit (Form-B)#New(2024-11-26)
    View
  • CA CERTIFICATE#New(2024-12-17)
    View
  • ARCHITECT CERTIFICATE#New(2024-12-03)
    View
  • ENGINEERS CERTIFICATE#New(2024-12-03)
    View
  • Other#New(2024-12-03)
    View
  • Proforma of Agreement for Sale#New(2024-11-26)
    View

Land documents

  • Sale Deed#21587(2024-07-08)
    13446585882.pdf
    View

Project Team

Architect Address405, Avalon Appt., New Mangalpuri, New Delhi-110030
Engineer AddressFirst Floor, 503/2, Old M.G. Road, Patel Nagar, Gurugram-122001

Developer & Contact

Developer

Promoter NameBP Infra India LLP
Promoter Address402, A-Wing, RAAS Building, Vasant Utsav C.H.S Ltd., Thakur Village, Kandivali (East), Mumbai – 400101
Company TypeLimited Liability Partnership (LLP)
Mobile9967062578
Emailaccounts.lko@bpinfragroup.com
Registered Address402, A-Wing, RAAS Building, Vasant Utsav C.H.S Ltd., Thakur Village, Kandivali (East), Mumbai – 400101
Contractor AddressSelf

Development & Facilities

Development works

Demarcation Of PlotsWe have one plot of size 10966.71 sq. mtr.having 1 main entrance gate from the 30 m wide front road.
Boundary Wall1.8 m high and 230 mm thick Brick work and rcc work in column and beam. At the center face of boundary wall there would be a Logo of the project which give a beautiful iconic design to boundary wall.
Road WorkFrom the main entrance gate we have 6.0 mtr wide driveay of 80 mm thick interlocking Pavers /RCC road through out the project.
FootpathsWe would not provide any footpath
Water Supply Including Drinking Water FacilitiesWe will provide 3 nos. of pump (2 working & 1 standby) for the requirement of blocks through underground pipelines.
Sewer SystemModular Sewerage system shall be Provided. All Sewerage water shall be go to the STP and overflow from the STP shall be connect with the Municipal sewerage system.when come into force. The capacity of STP will be 220 KLD.
DrainStorm water shall be Provided. Storm water from Roads and other landscape area shall be connect to the Storm water drain channel and go to the Rain water harvesting Pit for recharge the Ground water and overflow shall be connect with Municipal drain line.
ParksWe will provide green area with the different activities and the green area will have gaming facilities as/ sanctioned layout.
Tree PlantingWe will provide many type of trees all along the boundary wall & green area as/sanctioned layout
Design For Electric Supply Including Street LightingWe will design & implement the system as per local electricity Board and will consider centralized Transformer, HT panel, LT Panel, Feeder Pillar and DG backup for all DUs & common service like External lighting, Fountain, STP, Pump room etc.
Community BuildingsCommunity facilities with Gym, Games room, Party Hall and Activity hall would be provided
Treatment And Disposal System Of Sewage And Sullage WaterModular Sewerage system shall be Provided. All Sewerage water shall be go to the STP and overflow from the STP shall be connect with the Municipal sewerage system.,when come into force. The capacity of STP will be 220 KLD.
Solid Waste Management And Disposal SystemThere are a proper garbage collection area provided for the solid waste management.
Water Conservation SystemWe will suggest to individual to use low flow fixtures as well dual flush cistern and raw water harvesting system to reduce the water consumption and improve the ground water level.
Energy Management System Including Use Of Renewable EnergyWe will use LED lights fitting in external area as well as solar lights. In Pump room also all the equipment shall have energy efficient motor. And we will suggest to individual also to use.
Fire Protection And Fire Safety SystemWe will provide Fire Fighting facility in common areas while Individual owner can install their own system as per their and local authorities requirement.
Social Infrastructure And Other Public Amenities Including Public Health ServicesNA
Emergency Evacuation ServicesWe will have staircases which will be provided with emergency exits
Other Miscellaneous WorkNA

Financials

Registration Fee (₹)60000