GULSHAN AVANTE

by Gulshan Developers Private Limited

Gautam Buddha Nagar, Uttar Pradesh · UPRERAPRJ860880

Registered

Total units

96

Overview

Registration Date2023-06-10
RERA NumberUPRERAPRJ860880
Promoter IDUPRERAPRM210893
Proposed Start2023-05-05
Proposed Completion2028-04-30

Location

DistrictGautam Buddha Nagar
TehsilGautam Buddha Nagar
StateUttar Pradesh
Map unavailable — no coordinates on file.

Land Details

Project TypeNew
Total Units96
Unit Types3
Blocks2
Floors25

Khasra records (1)

  • GH-03A, Sector-16B, Greater Noida, Uttar Pradesh· Plot· 5417

Inventory

Apartments (55 rows)
BlockFloorTypeCountCarpet (m²)BalconyGarage
TOWER-AGFSHOP141.430
TOWER-AGFSHOP132.550
TOWER-AGFSHOP147.340
TOWER-AGFSHOP141.260
TOWER-A1OTHER000
TOWER-A24 BHK1164.253
TOWER-A24 BHK1164.252
TOWER-A34 BHK2164.253
TOWER-A44 BHK2164.253
TOWER-A54 BHK2164.253
TOWER-A64 BHK2164.253
TOWER-A74 BHK2164.253
TOWER-A84 BHK2164.253
TOWER-A94 BHK2164.923
TOWER-A124 BHK2164.253
TOWER-A134 BHK2164.253
TOWER-A144 BHK2164.253
TOWER-A154 BHK2164.250
TOWER-A164 BHK2164.253
TOWER-A104 BHK2164.253
TOWER-A174 BHK2164.253
TOWER-A184 BHK2164.253
TOWER-A194 BHK2164.253
TOWER-A204 BHK2164.253
TOWER-A214 BHK2164.253
TOWER-A224 BHK2164.253
TOWER-A234 BHK2164.253
TOWER-A244 BHK2164.253
TOWER-A114 BHK2164.253
TOWER-BGFOTHER000
TOWER-B1OTHER000
TOWER-B24 BHK1164.253
TOWER-B24 BHK1164.252
TOWER-B34 BHK2164.253
TOWER-B44 BHK2164.253
TOWER-B54 BHK2164.253
TOWER-B64 BHK2164.253
TOWER-B74 BHK2164.253
TOWER-B84 BHK2164.253
TOWER-B94 BHK2164.253
TOWER-B104 BHK2164.253
TOWER-B114 BHK2164.253
TOWER-B124 BHK2164.250
TOWER-B134 BHK2164.253
TOWER-B144 BHK2164.253
TOWER-B154 BHK2164.253
TOWER-B164 BHK2164.253
TOWER-B174 BHK2164.253
TOWER-B184 BHK2164.250
TOWER-B194 BHK2164.253
TOWER-B204 BHK2164.253
TOWER-B214 BHK2164.253
TOWER-B224 BHK2164.253
TOWER-B234 BHK2164.253
TOWER-B244 BHK2164.253

Permits & Approvals

Permit NoPLG/BP SM-27-May-2022/14563
Permit Date2023-05-02
Valid Until2028-05-01
Extendable Until2033-05-01

Documents

Filing documents

  • Other
  • Details of Encumbrances#New(2023-05-12)
    View
  • Commencement Certificate#New(2023-05-12)
    View
  • Other Plan(If Any)#New(2023-05-12)
    View
  • Proforma of Application Form#New(2023-05-12)
    View
  • Proforma of Allotment Letter#New(2023-05-12)
    View
  • Proforma of Conveyance Deed#New(2023-05-12)
    View
  • Proforma of Completion Certificate(Occupancy)#New(2023-05-12)
    View
  • Waste Disposal Plan#New(2023-05-12)
    View
  • Water Supply Plan#New(2023-05-12)
    View
  • Electricity Supply Plan#New(2023-05-12)
    View
  • Development Work Plan#New(2023-05-12)
    View
  • Affidavit (Form-B)#New(2023-05-12)
    View
  • CA CERTIFICATE#New(2023-05-12)
    View
  • ARCHITECT CERTIFICATE#New(2023-05-12)
    View
  • ENGINEERS CERTIFICATE#New(2023-05-12)
    View
  • Other#New(2023-05-20)
    View

Land documents

  • Registry Document#38597(2018-11-27)
    7500362219RegisteredLeaseDeed.pdf
    View

Project Team

Architect AddressB-99, First Floor, Sector 63, Noida-201301, Uttar Pradesh
Engineer AddressB-24, Sector 67, Noida-201301 U.P.

Developer & Contact

Developer

Promoter NameGulshan Developers Private Limited
Promoter AddressFLAT NO.-7, 3 FLOOR, PLOT NO.-4, DAYANAND VIHAR, EAST DELHI, DELHI- 110092
Company TypeCompany
Mobile9582255195
Emailgulshan.corp@gulshangroup.com
Registered AddressFLAT NO.-7, 3 FLOOR, PLOT NO.-4, DAYANAND VIHAR, EAST DELHI, DELHI- 110092
Contractor AddressFlat No-7, 3rd Floor, Plot No. 4, Dayanand Vihar, East Delhi, Delhi-110092

Bank Accounts

Account Typecollection
Account Number777705662801
Account NameGULSHAN DEVELOPERS PRIVATE LIMITED COLLECTION ACCOUNT FOR GULSHAN AVANTE
Bank NameICICI BANK LTD
BranchNOIDA SECTOR-137, NOIDA
Branch AddressSECTOR-137 , NOIDA GULSHAN VIVAVTE, NOIDA-201301
Branch DistrictGautam Buddha Nagar
Branch StateUttar Pradesh
IFSCICIC0003451
Account Typeseparate
Account Number777705662802
Account NameGULSHAN DEVELOPERS PRIVATE LIMITED SEPARATE BANK ACCOUNT FOR GULSHAN AVANTE
Bank NameICICI BANK LTD
BranchNOIDA SECTOR-137 NOIDA
Branch AddressSECTOR -137, NOIDA GULSHAN VIVANTE, NOIDA-201301
Branch DistrictGautam Buddha Nagar
Branch StateUttar Pradesh
IFSCICIC0003451
Account Typetransaction
Account Number777705662803
Account NameGULSHAN DEVELOPERS PRIVATE LIMITED TRANSACTION ACCOUNT FOR GULSHAN AVANTE
Bank NameICICI BANK LTD
BranchNOIDA SECTOR-137 NOIDA
Branch AddressSECTOR-137, NOIDA GULSHAN VIVANTE, NOIDA-201301
Branch DistrictGautam Buddha Nagar
Branch StateUttar Pradesh
IFSCICIC0003451

Development & Facilities

Development works

Demarcation Of PlotsAs per lease plan.
Boundary WallBrick Work and Permanent Furnishing on boundary wall of 7 feets height .
Road WorkCement concrete road with laying of pavers on top with the width of 7.5 meters .
FootpathsStone paving as per landscape architect plan Fire path way of 7.50 mtr.
Water Supply Including Drinking Water FacilitiesMunicipal water supply is collected in an underground storage reservoir. Underground storage of water is also required as reserve for firefighting purposes. It is proposed to provide static storage for firefighting as per the present requirements of NBC Over Head storage thanks are proposed to be placed on the terrace. It is proposed to have approximately half day requirement storage for fire fighting purposes also as per National Building code.
Sewer SystemThe soil waste from toilets kitchen will be collected in single network of sewer pipes laid underground having manholes/ inspection chambers at appropriate intervals. It is proposed to install sewage treatment plan on the site for treatment of sewage.
DrainThe Terrace and balconies of the buildings are proposed to be drained by means of down take pipes while open areas and roads would be drained in to drains. These drains are proposed to be aligned along the rods within the Complex as per the landscape design. The down take pipes from terraces and balconies would discharge in to the municipal drainage system after passing through rain water harvesting and ground water recharging structures.
ParksLandscaping of the parks with plantation including trees, shrubs and ground covers and recreational areas with benches and walkways. proposed landscape area in the project is 1044.907spmt.
Tree PlantingAs per landscape consultant / as per IGBC green building norms . One tree per 100 sqmt pf open area is proposed having approx 45 Trees in total.
Design For Electric Supply Including Street LightingThe Building shall be supplied power by the state Electricity Board. Since the source is unstable due to frequent brown out /black outs, it is proposed that full DG power backup shall be provided to all the common service and apartment. Some critical load such as emergency lighting headed equipment of ELV system etc. shall be additionally backed up using UPS battery backup system. the electrical power requirement for the project has been estimate based on 50 watt/ sq.mtr of built up areas, of the apartment ( As per up electricity ) lighting for streets, car park area , landscape areas, walkways (both covered and and uncovered) shall be automatically controlled by timer as per the time zone . LED shall be used to in all common area and external lighting to reduce power consumption.
Community BuildingsClub house as per plan having Multi purpose hall GYM Gaming Zone cafeteria spa / salon senior lounge.
Treatment And Disposal System Of Sewage And Sullage WaterIt is proposed to install sewage treatment plant on the site for treatment of sewage . The quantity of recycle water required in flushing horticulture shall be treated up to tertiary level and the balance total capacity of sewage treatment plant =100 KLD.
Solid Waste Management And Disposal SystemSegregation of soild waste and provision of Organic waste converter.
Water Conservation SystemA. The operation of pumps will be based on level sensors to ensure that water is not wasted and to avoid unnecessary operation of the equipment. B. Pumps equipment will be selected on best energy efficiency point. C. water conservation will be provided using low flow fixtures/ flow restrictors . D. Dual flush flushing cisterns will reduce water consumption. The water conservation in dual flush will be maximum 3 liters for low flush and 6 liters for high flush. E. sensor based urinals will be installed to ensure flushing only when in use to reduce the water consumption , F. provision of sewage treatment plant is proposed to treat 100 waste water generated. G. Recycle of treated effluent will reduce the total net fresh water demand of the project. Thereby reducing the load and dependency on municipal supply.
Energy Management System Including Use Of Renewable EnergyA. All lifts shall be provided with AC variable voltage variable frequency drives (ACVVF). B. Power factor shall be maintained 0.90 to unity . C. Astronomical Timers shall be used to switch ON/OFF street lighting and landscape lighting for power conservation. D. Timers shall be used to switch ON/OFF parking lights during non- Peak hours for power conservation. E. LED shall be used to in all common area and external lighting to reduce power consumption F. Controller based Synchronization along with PLC based load management is proposed to reduce the oil consumption and effective utilization of DG sets. G. All DG sets will be CPCB certified for noise and emissions.
Fire Protection And Fire Safety SystemThe project falls under Residential Buildings category A-4 ( Apartment) having height above 60 meters for apartment buildings. as per the nbc-2016 table 7, page 41and 42. Internal and external fire hydrant system shall be provide with landing valve hose reel with shut off nozzle short branch pipe with nozzle and fire mans axe . Automatic sprinklers system is provided. The system shall be suitably zoned for its optimum functional performance. sprinklers shall be distributed throughout the building as per the national building code and IS; 15105 requirements. In order to the fire / smoke in incipient stages an intelligent / Addressable automatic fire detection alarm system is proposed to be provided to cover all areas to provide timely warning to occupants to evacuate safely before the fire/ smoke spreads. The system shall be full zoned addressable, digital self- diagnostic and cover all internal and external areas.
Social Infrastructure And Other Public Amenities Including Public Health ServicesClub swimming pool etc.
Emergency Evacuation ServicesFire staircase /refuge area to be provided as per sanction plan .
Other Miscellaneous WorkCommercial space with in complex.

Financials

Registration Fee (₹)32500
Project Duration (months)60