GURU KRIPA SKY

by Maa Dholagarh Constructions (Proprietor- Shyam Singhal)

Mathura, Uttar Pradesh · UPRERAPRJ251029/01/2025

Registered

Total units

370

Overview

Registration Date2025-01-29
RERA NumberUPRERAPRJ251029/01/2025
Promoter IDUPRERAPRM301026
Proposed Start2024-10-01
Proposed Completion2029-09-12

Location

DistrictMathura
TehsilMathura
VillageMauja Sunrak Banger
AddressOn Khasra No. 1097(m), 1099(m), 1094(m), 1095, 1096, 1098(m), 1093
StateUttar Pradesh
Map unavailable — no coordinates on file.

Land Details

Project TypeNew
Total Units370
Unit Types4
Blocks6
Floors10

Khasra records (1)

  • 1097(m), 1099(m), 1094(m), 1095, 1096, 1098(m), 1093· Khasra· 1753750

Inventory

Apartments (92 rows)
BlockFloorTypeCountCarpet (m²)BalconyGarage
TOWER ABSMNTOTHER000
TOWER AGFOTHER000
TOWER A12 BHK968.583
TOWER A22 BHK968.583
TOWER A32 BHK968.583
TOWER A42 BHK968.583
TOWER A52 BHK968.583
TOWER A62 BHK968.583
TOWER A72 BHK968.583
TOWER A82 BHK968.583
TOWER BBSMNTOTHER000
TOWER BGFOTHER000
TOWER B12 BHK1168.583
TOWER B22 BHK1168.583
TOWER B32 BHK1168.583
TOWER B42 BHK1168.583
TOWER B52 BHK1168.583
TOWER B62 BHK1168.583
TOWER B72 BHK1168.583
TOWER CBSMNTOTHER000
TOWER CGFOTHER000
TOWER C11 BHK137.452
TOWER C12 BHK368.583
TOWER C13 BHK288.453
TOWER C21 BHK137.452
TOWER C22 BHK368.583
TOWER C23 BHK288.453
TOWER C31 BHK137.452
TOWER C32 BHK368.583
TOWER C33 BHK288.453
TOWER C41 BHK137.452
TOWER C42 BHK368.583
TOWER C43 BHK288.453
TOWER C51 BHK137.452
TOWER C52 BHK368.583
TOWER C53 BHK288.453
TOWER C61 BHK137.452
TOWER C62 BHK368.583
TOWER C63 BHK288.453
TOWER C71 BHK137.452
TOWER C72 BHK368.583
TOWER C73 BHK288.453
TOWER DBSMNTOTHER000
TOWER DGFOTHER000
TOWER D12 BHK768.583
TOWER D22 BHK768.583
TOWER D32 BHK768.583
TOWER D42 BHK768.583
TOWER D52 BHK768.583
TOWER D62 BHK768.583
TOWER D72 BHK768.583
TOWER EBSMNTOTHER000
TOWER EGFOTHER000
TOWER E12 BHK868.583
TOWER E22 BHK868.583
TOWER E32 BHK868.583
TOWER E42 BHK868.583
TOWER E52 BHK868.583
TOWER E62 BHK868.583
TOWER E72 BHK868.583
TOWER FBSMNTOTHER000
TOWER FGFOTHER000
TOWER F12 BHK668.583
TOWER F13 BHK188.453
TOWER F22 BHK668.583
TOWER F23 BHK188.453
TOWER F32 BHK668.583
TOWER F33 BHK188.453
TOWER F42 BHK668.583
TOWER F43 BHK188.453
TOWER F52 BHK668.583
TOWER F53 BHK188.453
TOWER F62 BHK668.583
TOWER F63 BHK188.453
TOWER F72 BHK668.583
TOWER F73 BHK188.453
TOWER B82 BHK368.5830
TOWER B13 BHK288.4530
TOWER B23 BHK288.4530
TOWER B33 BHK288.4530
TOWER B43 BHK288.4530
TOWER B53 BHK288.4530
TOWER B63 BHK288.4530
TOWER B73 BHK288.4530
TOWER A13 BHK188.4530
TOWER A23 BHK188.4530
TOWER A33 BHK188.4530
TOWER A43 BHK188.4530
TOWER A53 BHK188.4530
TOWER A63 BHK188.4530
TOWER A73 BHK188.4530
TOWER A83 BHK188.4530

Permits & Approvals

Permit NoGroup Housing/05139/MVDA/BP/23-24/1230/31052024
Permit Date2024-09-13
Valid Until2029-09-12
Extendable Until2032-09-11

Documents

Filing documents

  • Other Plan(If Any)
  • Proforma of Completion Certificate(Occupancy)
  • Other
  • Details of Encumbrances#New(2024-10-17)
    View
  • Commencement Certificate#New(2024-10-18)
    View
  • Proforma of Application Form#New(2024-10-18)
    View
  • Proforma of Allotment Letter#New(2024-10-18)
    View
  • Proforma of Conveyance Deed#New(2024-10-18)
    View
  • Waste Disposal Plan#New(2024-10-18)
    View
  • Water Supply Plan#New(2024-10-18)
    View
  • Electricity Supply Plan#New(2024-10-18)
    View
  • Development Work Plan#New(2024-10-18)
    View
  • Affidavit (Form-B)#New(2024-10-18)
    View
  • CA CERTIFICATE#New(2024-11-07)
    View
  • ARCHITECT CERTIFICATE#New(2024-10-18)
    View
  • ENGINEERS CERTIFICATE#New(2024-10-18)
    View
  • Other#New(2024-12-09)
    View
  • Proforma of Agreement for Sale#New(2024-10-18)
    View

Land documents

  • Registry Document#13673(2024-05-17)
    13046126775.pdf
    View

Project Team

Architect AddressH.No. 2, Jamuna Vihar Colony, Near Central Bank, Masani, Mathura
Engineer AddressS/o Vinod Shastri, Mawali, Post Panigaon, Mant, Mathura

Developer & Contact

Developer

Promoter NameMaa Dholagarh Constructions (Proprietor- Shyam Singhal)
Promoter AddressMayur Vihar, 68, Dholi Pyau, Mathura, Mathura, Uttar Pradesh, 281001
Company TypeProprietorship Firm
Mobile9760031311
Emailshysinghal88@gmail.com
Registered AddressMayur Vihar, 68, Dholi Pyau, Mathura, Mathura, Uttar Pradesh, 281001
Contractor AddressH.No. 364, Mathura Darwaza, Vrindavan Bangar, Vrindavan Mathura, 281121

Bank Accounts

Account Typecollection
Account Number924020032168087
Account NameMAA DHOLAGARH CONSTRUCTIONS-GURU KRIPA SKY - COLLECTION ACCOUNT
Bank NameAXIS BANK LIMITED
BranchMATHURA, UTTAR PRADESH
Branch AddressOJAL MALL MATHURA, U.P
Branch DistrictMathura
Branch StateSelect
IFSCUTIB0000359
Branch EmailMATHURA.BRANCHHEAD@AXISBANK.COM
Account Typeseparate
Account Number924020036322425
Account NameMAA DHOLAGARH CONSTRUCTIONS-GURU KRIPA SKY- SEPARATE ACCOUNT
Bank NameAXIS BANK LIMITED
BranchMATHURA, UTTAR PRADESH
Branch AddressOJAL MALL MATHURA-281001
Branch DistrictMathura
Branch StateUttar Pradesh
IFSCUTIB0000359
Account Typetransaction
Account Number924020049723783
Account NameMAA DHOLAGARH CONSTRUCTIONS- RERA TRANSACTION ACCOUNT FOR GURU KRIPA SKY
Bank NameAXIS BANK LIMITED
BranchMATHURA, UTTAR PRADESH
Branch AddressOJAL Mall , MATHURA 282001
Branch DistrictMathura
Branch StateUttar Pradesh
IFSCUTIB0000359

Development & Facilities

Development works

Demarcation Of PlotsThe project land will be clearly demarcted on land with the project boundary wall. The building lines and the setbacks from the periphery to the building line will be maintained as per the byelaws.
Boundary WallA 8 feet high boundary wall will be constructed for the project. The foundation of the boundary wall will be earthquake resistant. The wall will be constructed in brick and mortar with reinforced columns at specified intervals. The wall will be plastered and painted.
Road WorkThe concrete road will be constructed in the project. The 200 mm CC layer will be laid over DLC and GSB. The surface texturing will be done to ensure antiskid paving surface.
FootpathsThe interlocking paver blocks will be laid to the minimum width of 1m. The M-20 paver blocks of the depth 60-80 mm will be laid for the footpath. The footpsth will be on the periphery of the parks and at all suitable locations to encourage walking by the residents.
Water Supply Including Drinking Water FacilitiesThe ground water will be pumped to the underground water take of minimum 10000 kl. Thereon the water will be pumped to the terrace tanks. From treerace tanks the water will be supplied to each unit and common areas of the project. The pipe line will be rust free PVC pipes of sufficient diameter to cater the domestic requuirements of the project.
Sewer SystemThe sewer syster , vertical and horizontal will be installed in the project to cater for the domestic and common area sewer. The soil pipes will be installed along with the syphon and inspection chambers at all floor levels. The sewer line will be led to the chmambers at the ground level. Thereon the sewer will be lead to the STP
DrainThe sub surface dain and the storm water drains will be constructed in the project. The roof top water will be catered for the RWH. The wate for domestic drain will be separately catered and will be connected to ground drainage system leading to the outlet as per local norms and guidelines.
ParksThe parks will be constructed as per the landscape plan. The lush green parks will be developed in the project along with amenities for the kids and elders.
Tree PlantingThe trees suitable to the local soil will be planted in the project along the parks periphery and boundary wall. the tress will also be planted at all suitable locations.
Design For Electric Supply Including Street LightingSeparate transformer will be installed for the project as per the approved load / sanvtioned load by DVVNL. The ISI maerked electric llines (majorly concealed) will lead to all the individual units through distribution boxes. The street and common lighting will ensure that the common areas are always sufficiently lit.
Community BuildingsN.A
Treatment And Disposal System Of Sewage And Sullage WaterAn STP will be installed in the project. The multi chamber STP will be sufficient to cater for the neeeds of the project. The sewage will go through the stage treatements of screening , sedimentation and biological treatement. The watewater will be bought to the safe levels before being disposed.
Solid Waste Management And Disposal SystemThe wate chute along with multiple garbage bins will be installed at all floors and at all suitable location of the project. The domestic wate will be collected as per category and will be disosed at the pre defined location by the local administrative body.
Water Conservation SystemThe rain water harvestin pit will be constructed/ installed in the project to arrest the terrace water and the surfce water . The same will be lead to the collection chambe r and will move through the multi stage filteration system. The collected filtered water will be led though the perforated pipe of 100 dia. to the ground water. The part of this water will be used for the parks etc.
Energy Management System Including Use Of Renewable EnergyAlthough not specified in the project , the usage of green technologies along with the LED lights will be installed in the project.
Fire Protection And Fire Safety SystemThe intalations of the fire extinguishers will be done at all required loctions of the projecct. A separate water tank will be constructed for the purpose of fire fighting. The fire hydrants, sprinklers and alarm system will be put in place. The buiding will have the emergency exit to ensure safe egress of the residents from the building in case of fire.
Social Infrastructure And Other Public Amenities Including Public Health ServicesNot Applicable
Emergency Evacuation ServicesThe Stairwell will be developed in a manner to create safe passage in case of emergency in the building. The riser will be constructed considering the old ge and yougs .
Other Miscellaneous WorkAs per the project requirements

Financials

Registration Fee (₹)82500
Project Duration (months)60