Registered
Total units
247
Overview
Registration Date2023-11-28
RERA NumberUPRERAPRJ850664
Promoter IDUPRERAPRM257672
Proposed Start2023-09-12
Proposed Completion2028-09-11
Location
DistrictLucknow
TehsilSarojini Nagar
StateUttar Pradesh
Map unavailable — no coordinates on file.
Land Details
Project TypeNew
Total Units247
Unit Types2
Blocks1
Floors5
Khasra records (4)
- 26.45.38.96 N, 80.55.23.36 E· Plot· 0 m²
- 26.45.41.13 N, 80.55.23.33 E· Plot· 0 m²
- 26.45.38.00 N, 80.55.21.54 E· Plot· 0 m²
- 26.45.39.97 N, 80.55.19.72 E· Plot· 5593 m²
Inventory
Apartments (57 rows)
| Block | Floor | Type | Count | Carpet (m²) | Balcony | Garage |
|---|---|---|---|---|---|---|
| Tower-1 | BSMNT | SHOP | 1 | 30.199 | 0 | — |
| Tower-1 | BSMNT | SHOP | 17 | 29.988 | 0 | — |
| Tower-1 | BSMNT | SHOP | 1 | 56.7 | 0 | — |
| Tower-1 | BSMNT | SHOP | 1 | 17.173 | 0 | — |
| Tower-1 | BSMNT | SHOP | 16 | 19.448 | 0 | — |
| Tower-1 | BSMNT | SHOP | 1 | 23.71 | 0 | — |
| Tower-1 | BSMNT | SHOP | 1 | 17.24 | 0 | — |
| Tower-1 | BSMNT | SHOP | 7 | 13.149 | 0 | — |
| Tower-1 | BSMNT | SHOP | 4 | 8.829 | 0 | — |
| Tower-1 | BSMNT | SHOP | 1 | 13.922 | 0 | — |
| Tower-1 | BSMNT | SHOP | 11 | 13.149 | 0 | — |
| Tower-1 | BSMNT | SHOP | 7 | 13.77 | 0 | — |
| Tower-1 | BSMNT | SHOP | 1 | 10.36 | 0 | — |
| Tower-1 | BSMNT | SHOP | 7 | 8.829 | 0 | — |
| Tower-1 | BSMNT | SHOP | 1 | 13.22 | 0 | — |
| Tower-1 | GF | SHOP | 1 | 30.199 | 0 | — |
| Tower-1 | GF | SHOP | 17 | 29.988 | 0 | — |
| Tower-1 | GF | SHOP | 1 | 56.7 | 0 | — |
| Tower-1 | GF | SHOP | 1 | 17.173 | 0 | — |
| Tower-1 | GF | SHOP | 16 | 19.448 | 0 | — |
| Tower-1 | GF | SHOP | 1 | 23.71 | 0 | — |
| Tower-1 | GF | SHOP | 1 | 25.2 | 0 | — |
| Tower-1 | GF | SHOP | 7 | 13.149 | 0 | — |
| Tower-1 | GF | SHOP | 4 | 8.829 | 0 | — |
| Tower-1 | GF | SHOP | 1 | 14.29 | 0 | — |
| Tower-1 | GF | SHOP | 11 | 13.149 | 0 | — |
| Tower-1 | GF | SHOP | 7 | 13.77 | 0 | — |
| Tower-1 | GF | SHOP | 1 | 10.36 | 0 | — |
| Tower-1 | GF | SHOP | 2 | 13.77 | 0 | — |
| Tower-1 | GF | SHOP | 1 | 10.36 | 0 | — |
| Tower-1 | GF | SHOP | 10 | 8.829 | 0 | — |
| Tower-1 | GF | SHOP | 1 | 13.22 | 0 | — |
| Tower-1 | 1 | SHOP | 1 | 30.199 | 0 | — |
| Tower-1 | 1 | SHOP | 8 | 29.988 | 0 | — |
| Tower-1 | 1 | SHOP | 2 | 49.833 | 0 | — |
| Tower-1 | 1 | SHOP | 7 | 29.988 | 0 | — |
| Tower-1 | 1 | SHOP | 1 | 56.7 | 0 | — |
| Tower-1 | 1 | SHOP | 1 | 17.173 | 0 | — |
| Tower-1 | 1 | SHOP | 7 | 19.448 | 0 | — |
| Tower-1 | 1 | SHOP | 2 | 32.318 | 0 | — |
| Tower-1 | 1 | SHOP | 7 | 19.448 | 0 | — |
| Tower-1 | 1 | SHOP | 1 | 23.71 | 0 | — |
| Tower-1 | 1 | SHOP | 1 | 25.2 | 0 | — |
| Tower-1 | 1 | SHOP | 7 | 13.149 | 0 | — |
| Tower-1 | 1 | SHOP | 4 | 8.829 | 0 | — |
| Tower-1 | 1 | SHOP | 1 | 14.29 | 0 | — |
| Tower-1 | 1 | SHOP | 11 | 13.149 | 0 | — |
| Tower-1 | 1 | SHOP | 7 | 13.77 | 0 | — |
| Tower-1 | 1 | SHOP | 1 | 10.36 | 0 | — |
| Tower-1 | 1 | SHOP | 2 | 13.77 | 0 | — |
| Tower-1 | 1 | SHOP | 1 | 10.36 | 0 | — |
| Tower-1 | 1 | SHOP | 10 | 8.829 | 0 | — |
| Tower-1 | 1 | SHOP | 1 | 13.22 | 0 | — |
| Tower-1 | 2 | OTHER | 1 | 1097.38 | 0 | — |
| Tower-1 | 2 | OTHER | 1 | 311.14 | 0 | — |
| Tower-1 | 3 | OTHER | 1 | 155.7436 | 0 | — |
| Tower-1 | 3 | OTHER | 1 | 155.7436 | 0 | — |
Permits & Approvals
Permit NoCommercial Building/08927/LDA/BP/22-23/3826/29072023
Permit Date2023-09-12
Valid Until2028-09-11
Extendable Until2028-09-11
Documents
Filing documents
- Other Plan(If Any)
- Proforma of Completion Certificate(Occupancy)
- CA CERTIFICATE
- ARCHITECT CERTIFICATE
- ENGINEERS CERTIFICATE
- Details of Encumbrances#New(2023-09-26)View
- Commencement Certificate#New(2023-09-26)View
- Proforma of Application Form#New(2023-09-22)View
- Proforma of Allotment Letter#New(2023-09-22)View
- Proforma of Conveyance Deed#New(2023-09-22)View
- Waste Disposal Plan#New(2023-09-23)View
- Water Supply Plan#New(2023-09-23)View
- Electricity Supply Plan#New(2023-09-23)View
- Development Work Plan#New(2023-09-23)View
- Affidavit (Form-B)#New(2023-09-21)View
- CA CERTIFICATE#New(2023-10-07)View
- ARCHITECT CERTIFICATE#New(2023-10-07)View
- ENGINEERS CERTIFICATE#New(2023-10-07)View
- Other#New(2023-09-21)View
Land documents
- Sale Deed#17290(2012-09-20)View8597651334Registry 1- Omaxe to Mani Infradev.pdf
- Sale Deed#37324(2022-10-10)View8597653992Registry 2- Mani Infradev to Marigold Buildcon.pdf
- Extract of Khatauni#Affidavit Cum Undertaking For Registration Of Project Under RERA(1900-01-01)View8597653293Affidavit Cum Undertaking For Registration Of Project Under RERA (1).pdf
Project Team
Architect Address4/119 , Virat Khand, Lucknow
Engineer AddressNauranga Rath, Hamirpur, Uttar Pradesh-210428
Developer & Contact
Developer
Promoter NameMarigold Buildcon
Promoter Address47/16, Clay Square, Kabir Marg, Lucknow, Uttar Pradesh- 226001
Company TypePartnership Firm
Mobile9984595468
Emailmarigoldbuildcon@gmail.com
Registered Address47/16, Clay Square, Kabir Marg, Lucknow, Uttar Pradesh- 226001
Contractor AddressB-3, Baba Complex, Sector-23, Sanjay Nagar, Ghaziabad, Uttar Pradesh
Bank Accounts
Account Typecollection
Account Number120024748958
Account NameMB COLLECTION ACCOUNT FOR KAILASHA AWADH
Bank NameCANARA BANK
BranchSECTOR-8, INDIRA NAGAR, LUCKNOW
Branch AddressLITTLE ANGELS HIGH SCHOOL, SECTOR- 8, INDIRA NAGAR, LUCKNOW, UTTAR PRADESH- 226016
Branch DistrictLucknow
Branch StateUttar Pradesh
IFSCCNRB0018487
Account Typeseparate
Account Number120024727526
Account NameMB SEPARATE ACCOUNT FOR KAILASHA AWADH
Bank NameCANARA BANK
BranchSECTOR-8, INDIRA NAGAR, LUCKNOW
Branch AddressLITTLE ANGELS HIGH SCHOOL, SECTOR- 8, INDIRA NAGAR, LUCKNOW, UTTAR PRADESH- 226016
Branch DistrictLucknow
Branch StateUttar Pradesh
IFSCCNRB0018487
Account Typetransaction
Account Number120024676621
Account NameMB TRANSACTION ACCOUNT FOR KAILASHA AWADH
Bank NameCANARA BANK
BranchSECTOR-8, INDIRA NAGAR, LUCKNOW
Branch AddressLITTLE ANGELS HIGH SCHOOL, SECTOR- 8, INDIRA NAGAR, LUCKNOW, UTTAR PRADESH- 226016
Branch DistrictLucknow
Branch StateUttar Pradesh
IFSCCNRB0018487
Development & Facilities
Development works
Demarcation Of PlotsWe have one plot of size 5592.52 sq. mtr.having 1 main entrance gate from the 24 m wide front road.
Boundary Wall2Mtr High Precast Rcc Boundary wall at the center face of boundary wall there would be a Logo of the project which give a beautiful iconic design to boundary wall.
Road WorkFrom the main entrance gate we will make 80 mm thick interlocking brick /RCC road through out the project. Whose wideness starts from 6 - 10 mtr.
FootpathsNA
Water Supply Including Drinking Water FacilitiesWe will provide Two nos. of pump for the requirement of blocks through underground pipelines.
Sewer SystemModular Sewerage system shall be Provided. All Sewerage water shall be go to the STP and overflow from the STP shall be connect with the Municipal sewerage system.when come into force.
DrainStorm water shall be Provided. Storm water from Roads and other landscape area shall be connect to the Storm water drain channel and go to the Rain water harvesting Pit for recharge the Ground water and overflow shall be connect with Municipal drain line.
ParksNA
Tree PlantingWe will provide many type of trees all along the boundary wall & green area
Design For Electric Supply Including Street LightingWe will design & implement the system as per local electricity Board and will consider centralized Transformer, HT panel, LT Panel, Feeder Pillar and DG back for common service like External lighting, Fountain, STP, Pump room etc.
Community BuildingsNA
Treatment And Disposal System Of Sewage And Sullage WaterModular Sewerage system shall be Provided. All Sewerage water shall be go to the STP and overflow from the STP shall be connect with the Municipal sewerage system.,when come into force.
Solid Waste Management And Disposal SystemThere are a proper garbage collection area provided for the solid waste management.
Water Conservation SystemWe will suggest to individual to use low flow fixtures as well dual flush cistern and raw water harvesting system to reduce the water consumption and improve the ground water level.
Energy Management System Including Use Of Renewable EnergyWe will use LED lights fitting in external area as well as solar lights. In Pump room also all the equipment shall have energy efficient motor. And we will suggest to individual also to use.
Fire Protection And Fire Safety SystemFire protection will be provides as per By-lays and Guidelines of Fire Dept.
Social Infrastructure And Other Public Amenities Including Public Health ServicesNA
Emergency Evacuation ServicesWe will have staircases which will be provided with emergency exit doors and emergency exit gates
Other Miscellaneous WorkNA
Financials
Registration Fee (₹)66000
Project Duration (months)60