NEW SUNCITY EXT-P3

by CITIZEN HOUSING AND DEVELOPING COOPERATIVE SOCIETY

Prayagraj, Uttar Pradesh · UPRERAPRJ907325/09/2024

Registered

Overview

Registration Date2024-09-05
RERA NumberUPRERAPRJ907325/09/2024
Promoter IDUPRERAPRM9349
Proposed Start2024-01-10
Proposed Completion2029-01-01

Location

DistrictPrayagraj
TehsilPhulpur
VillageJHUNSI
AddressMAUJA ANDAWA & BADHAWA TAHIRPUR
StateUttar Pradesh
Map unavailable — no coordinates on file.

Land Details

Project TypeNew
Plots25

Khasra records (8)

Show all 8 khasra rows
  • 1027· Khasra· 855
  • 1028· Khasra· 1030
  • 1032· Khasra· 230
  • 1033· Khasra· 285
  • 1042· Khasra· 740
  • 1043· Khasra· 610
  • 1044· Khasra· 700
  • 1085· Khasra· 520

Inventory

Plots

TypeSize rangeCount
PlotUPTO 100 sqm11
Plot100 to 150 sqm12
Plot150 to 200 sqm2

Permits & Approvals

Permit No02/O.C.(T.C.)/ZONE-5/INTEGRATED/DEV.AUTH/2023-24/DATED 10/01/2024
Permit Date2024-01-10
Valid Until2029-01-09
Extendable Until2029-01-09

Documents

Filing documents

  • Details of Encumbrances#New(2024-07-17)
    View
  • Commencement Certificate#New(2024-07-17)
    View
  • Other Plan(If Any)#New(2024-08-08)
    View
  • Proforma of Application Form#New(2024-07-17)
    View
  • Proforma of Allotment Letter#New(2024-08-08)
    View
  • Proforma of Conveyance Deed#New(2024-07-17)
    View
  • Waste Disposal Plan#New(2024-07-17)
    View
  • Water Supply Plan#New(2024-07-17)
    View
  • Electricity Supply Plan#New(2024-07-17)
    View
  • Development Work Plan#New(2024-07-17)
    View
  • Affidavit (Form-B)#New(2024-07-17)
    View
  • CA CERTIFICATE#New(2024-07-17)
    View
  • ARCHITECT CERTIFICATE#New(2024-07-17)
    View
  • ENGINEERS CERTIFICATE#New(2024-07-17)
    View
  • Other#New(2024-08-08)
    View
  • Proforma of Agreement for Sale#New(2024-07-17)
    View

Land documents

  • Registry Document#1992(2018-05-25)
    11655641960.pdf
    View
  • Registry Document#2304(2019-03-12)
    11655643306.pdf
    View
  • Registry Document#2785(2019-03-28)
    11655647772.pdf
    View
  • Registry Document#5441(2015-06-27)
    11655644726.pdf
    View
  • Registry Document#2058(2019-05-02)
    11655644648.pdf
    View
  • Registry Document#7422(2019-08-09)
    11655642821.pdf
    View
  • Registry Document#8445(2020-11-03)
    11655646114.pdf
    View
  • Registry Document#6523(2021-07-24)
    11655645823.pdf
    View
  • Registry Document#11694(2021-12-03)
    11655644786.pdf
    View
  • Registry Document#11697(2021-12-03)
    11655645026.pdf
    View
  • Registry Document#412(2022-01-15)
    11655646866.pdf
    View
  • Registry Document#9306(2022-08-24)
    11655647890.pdf
    View
  • Registry Document#9304(2022-08-24)
    11655642741.pdf
    View
  • Registry Document#10702(2022-09-26)
    11655649535.pdf
    View
  • Registry Document#10704(2022-09-26)
    11655643573.pdf
    View
  • Registry Document#10705(2022-09-26)
    11655641014.pdf
    View
  • Registry Document#11344(2022-10-11)
    11655645934.pdf
    View
  • Registry Document#11342(2022-10-11)
    11655642689.pdf
    View
  • Registry Document#11343(2022-10-11)
    11655649385.pdf
    View
  • Registry Document#1307(2023-02-10)
    11655647651.pdf
    View
  • Registry Document#1308(2023-02-10)
    11655647281.pdf
    View
  • Registry Document#3540(2023-04-18)
    11655649933.pdf
    View
  • Registry Document#BAHI4/JILD601/PAGE229-258/SR102(2024-03-12)
    11655645793.pdf
    View

Project Team

Architect Address139, ALLENGANJ, PRAYAGRAJ, UTTAR PRADESH
Engineer Address139, ALLENGANJ, PRAYAGRAJ, UTTAR PRADESH

Developer & Contact

Developer

Promoter NameCITIZEN HOUSING AND DEVELOPING COOPERATIVE SOCIETY
Promoter AddressSAHYOG BHAWAN, 1 MG MARG, CIVIL LINES, ALLAHABAD
Company TypeSocieties
Mobile9335155202
Emailnishithverma.ald@gmail.com
Registered AddressSAHYOG BHAWAN, 1 MG MARG, CIVIL LINES, ALLAHABAD
Contractor Address14 IBRAHIMPUR, TRIVENIPURAM, JHUNSI, PRAYAGRAJ-211019

Bank Accounts

Account Typecollection
Account Number7820741242
Account NameCITIZEN HOUSING DEV COSO-COLLECTION AC FOR NEWSUNCITY EXT-P3
Bank NameINDIAN BANK
BranchHINDI SAHITYA SAMMELAN BRANCH
Branch Address12 KP KAKKAR ROAD PRAYAGRAJ -211003
Branch DistrictPrayagraj
Branch StateSelect
IFSCIDIB000A580
Branch Emaila580@indianbank.co.in
Account Typeseparate
Account Number7820741424
Account NameCITIZEN HOUSING DEV COSO-SEPARATE AC FOR NEW SUNCITY EXT-P3
Bank NameINDIAN BANK
BranchHINDI SAHITYA SAMMELAN BRANCH
Branch Address12 KP KAKKAR ROAD PRAYAGRAJ 211003
Branch DistrictPrayagraj
Branch StateUttar Pradesh
IFSCIDIB000A580
Account Typetransaction
Account Number7820741377
Account NameCITIZEN HOUSING DEV COSO TRANSACTION AC FOR NEWSUNCITY EXT-P3
Bank NameINDIAN BANK
BranchHINDI SAHITYA SAMMELAN BRANCH
Branch Address12 KP KAKKAR ROAD PRAYAGRAJ 211003
Branch DistrictPrayagraj
Branch StateUttar Pradesh
IFSCIDIB000A580

Development & Facilities

Development works

Demarcation Of PlotsAS PER APPROVED MAP A TOTAL OF 25 PLOTS ARE BEING DEVELOPED OUT VARIOUS SIZES. DEMARCATION OF PLOT WILL BE DONE WITH 5 FT (4 INCH) BRICK WORK
Boundary WallTHE EXTENSION-P3 IS CONJUNCTION WITH LARGER INTEGRATED TOWNSHIP WHICH IS DEVELOPED WITH SINGLE ENTRY AND EXIT. THE TOWNSHIP IS BOUNDED BY COMPOUND WALL ACROSS THE TOWNSHIP. THE SAID BOUNDARY WALL IS CONSTRUCTED WITH 9 INCH BRICK WORK AND 6 FT IN HEIGHT. THE CONSTRUCTION IS DONE WITH FLY-ASH/RED BRICK USING CEMENT MORTAR 1-6 RATIO.
Road WorkAS PER DPR OF THE PROJECT ROAD NETWORK IS DEVELOPED ACROSS THE PROJECT IN HIERARCHY FROM 15 MTR., 12 MTR AND 9 MTR. ROAD CONSTRUCTION IS CARRIED OUT WITH BASIC EARTH WORK FOLLOWED BY WBM, GSB, AND STONE DUST FOLLOWED WITH EXTENSIVE COMPACTION THEREAFTER GANGA SAND (2 INCH THICK BED) IS LAID AND THEREAFTER FINISHED WITH INTERLOCKING PAVERS.
FootpathsTHE FOOTPATHS HAVE BEEN DESIGNED TO CARRY SEVER (6 INCH HUME PIPE). WATER LINE (2 INCH UPVC). STORM WATER (6 INCH PVC PIPE) DRAIN PIPE. ALL TEHSE SERVICES ARE UNDERGROUND. THE FOOTPATH IS CONSTRUCTED USING CHEQURED TILES (1FTX1FT) WITH KERB STONE (12 INCH WIDE). AVENUE TREES AND ELECTRICAL POLES (9M AND 11M) ARE INSTALLED ADJACENT TO THESE FOOTPATHS.
Water Supply Including Drinking Water FacilitiesELEVATED WATER TANK OF 125000 LTR CAPACITY FED BY 6 HP BORE WELL PUMPS IN REDUNDANCY ARRANGEMENT IS ALSO MADE FOR CHLORINE DOZING TO DISTRIBUTE PORTABLE WATER TO HOUSEHOLDS A NETWORK OF 2 INCH UPVC PIPES ARE LAID UNDER GROUND FOR WATER SUPPLY WITHIN THE TOWNSHIP.
Sewer SystemA NETWORK OF UNDERGROUND 6 INCH HUME PIPE HAVE BEEN LAID TO CARRY SEVERAGE FROM HOUSE HOLD TO STP PLACED WITHIN THE TOWNSHIP THE TOWNSHIP IS PLANNED AS A ZERO DISCHARGE DEVELOPMENT. DECENTRALIZED PACKAGED STPs OF 40 KLD EACH AS PER SECTOR ARE AS DETAIL ED IN PROJECT DPR ARE BEING COMMISSIONED. THESE PACKAGED STPs ARE BASED ON ANAEROBIC PROCESS TO BREAK-DOWN SEWER AND SLUDGE WASTE.
DrainROOF TOP RUN OFF AND KITCHEN WASTE WATER IS DRAINED FROM ROAD AREAS AND HOUSEHOLDS THROUGH 6 INCH PVC PIPES WHICH ARE LAID UNDERGROUND DEPENDING UPON THE CLASSIFICATION OF WASTE WATER IT IS EVENTUALLY DRAINED INTO RAIN WATER HARVESTING PITS (4 NOS), SCREENING FILTERS OR ARTIFICIAL POND (1720 SQ MTR) DEVELOPED WITHIN THE TOWNSHIP.
ParksPARKS AND GREEN AREA HAVE BEEN DEVELOPED WITHIN THE TOWNSHIP AS PER APPROVED MAP. THE TOWNSHIP HAS A PARKS EARMARKED FOR SENIOR CITIZENS WITH SPACE FOR YOGA AND SEATING ARRANGEMENT AND FLOWERING PLANTS AND SHRUBS. SIMILARLY A CHILDREN PARK WITH PLAY STATION AND WALK THROUGH FOUNTAIN HAS BEEN DEVELOPED A SPORT CENTER AS PER THE DENSITY NORMS OF THE TOWNSHIP. IT HAS BEEN DEVELOPED WITH CRICKET GROUND, FOOTBALL FIELD, BASKET BALL, VOLLEYBALL, BADMINTON COURT AND SWIMMING POOL. THIS SPORT CENTER DEVELOPED OVER 2.5 ACRE LAND AND OPEN AIR GYM IS MADE OVER 250 SQ MTR. LAND.
Tree PlantingMORE THAN 700 TREES HAVE BEEN PLANTED WITHIN THE TOWNSHIP. AVENUE TREE SUCH AS GULMOHAR CHITWAN AND AMALTAS ETC. AND BUSHES AND HEDGES HAVE BEEN PLANTED IN HIERARCHICAL ORDER FLOWERING PLANTS AND EVERGREEN PLANTS HAVE BEEN PLANTED IN OPEN AREAS, PARKS AND OTHER INSTALLATION.
Design For Electric Supply Including Street LightingELECTRIC POLES WITH LED STREET LIGHTS ARE PLACED AT 60 FT TO 80 FT INTERVAL. EACH STREET LIGHT INSTALLED WITH WATTAGE OF 100 WATT OR 200 WATT AS PER REQUIREMENT A TOTAL OF OVER 250 SUCH STREETS HAVE BEEN INSTALLED WITHIN THE TOWNSHIP.
Community BuildingsCONSTRUCTION OF COMMUNITY HALL/FUNCTION HALL, MULTI PURPOSE HALL WITH KITCHEN HAS BEEN CONSTRUCTED OVER A PLOT SIZE OF 600 SQ MTR (INCLUDING PARKING). THE BUILDING ALSO HOUSES A MODERN GYM AND INDOOR GAMES ROOM.
Treatment And Disposal System Of Sewage And Sullage WaterDECENTRALIZED PACKAGED STPs 40 KLD EACH IS BEING INSTALLED AS PER DPR IN VARIOUS SECTORS OF THE TOWNSHIP SEWAGE AND SULLAGE WATER WILL BE CARRIED FROM HOUSEHOLDS THROUGH UNDERGROUND SERVICES PIPE TO THE SPTs THE TREATED WATER FROM THE STP USED TO IRRIGATION OR SENT TO THE ARTIFICIAL POND (1720 SQ MTR) DEVELOPED WITHIN THE TOWNSHIP.
Solid Waste Management And Disposal SystemDECENTRALIZED PACKAGED STPs 40 KLD EACH IS BEING INSTALLED AS PER DPR IN VARIOUS SECTORS OF THE TOWNSHIP. THESE STPs WORK ON ANAEROBIC PROCESS TO BREAK-DOWN SOLID WASTE AND FILTERED WATER IS RECEIVED FROM THE INCOMING GRAY WATER. THE FILTERED WATER USED FOR IRRIGATION AND WASHING ROADS( POLLUTION CONTROL).
Water Conservation SystemRAIN WATER HARVESTING SYSTEM HAS BEEN DEVELOPED AT FOUR LOCATIONS WITHIN THE TOWNSHIP AND STIPULATED NOC FROM GROUND WATER DEPARTMENT HAS BEEN RECEIVED. RWH PITS OF 50 CuMT, 35 CuMT, 65 CuMT, 40CuMT, ALONG WITH FILTERS HAS BEEN DEVELOPED FOR THE TOWNSHIP.
Energy Management System Including Use Of Renewable EnergyTHE TOWNSHIP HAS SANCTIONED LOAD OF 1558 KW FROM PuVVNL PRAYAGRAJ. INDIVIDUAL HOUSEHOLDS ARE SUPPLIED WITH ELECTRICAL CONNECTION FROM THE DEPARTMENT. FIVE SOCIETY CONNECTION RANGING FROM 5 KW TO 10 KW HAVE BEEN TAKEN FOR DIFFERENT PURPOSES WITHIN THE TOWNSHIP SUCH AS STREET LIGHT, PUMP ROOM, TEMPLE AND COMMON AREA ETC.
Fire Protection And Fire Safety SystemREQUISITE FIRE PROTECTION SYSTEM HAS BEEN DEVELOPED AS PER REQUIREMENT. BEING A PLOTTED DEVELOPMENT PROJECT THE REQUIREMENT OF FIRE PROTECTION IS LIMITED. HOWEVER 10 FIRE HYDRANT AND SAND BUCKETS HAVE BEEN PLACED AT VARIOUS ACCESSIBLE AREAS. EVACUATION AREA HAVE BEEN EARMARKED AT FIVE LOCATION WITHIN THE TOWNSHIP.
Social Infrastructure And Other Public Amenities Including Public Health ServicesSTIPULATED IN THE INTEGRATED TOWNSHIP POLICY LAND HAS BEEN EARMARKED AND PROVISION HAS BEEN MADE FOR NURSING HOMES, SCHOOL ETC. WITHIN THE TOWNSHIP WHERE RESIDENT CAN AVAIL SERVICES ON PAYMENT BASIS.
Emergency Evacuation ServicesFIVE NUMBERS EMERGENCY EVACUATION AREAS HAVE BEEN EARMARKED IN OPEN SPACES SUCH AS PARKS AND TOT-LOTS. WITH A CAPACITY TO HOLD MINIMUM 100 PERSONS AT A TIME IN CASE OF REQUIREMENT. BEING A PLOTTED DEVELOPMENT PROJECT THE NEED FOR SUCH SERVICES ARE MINIMAL.
Other Miscellaneous WorkUNDER THE INTEGRATED TOWNSHIP POLICY OF THE UP GOVERNMENT. DETAILED PROJECT REPORT (DPR)HAS BEEN APPROVED BY PRAYAGRAJ DEVELOPMENT AUTHORITY AND DEVELOPMENT AGREEMENT HAS BEEN SIGNED WITH PDA. ALL DEVELOPMENT NORMS, RULES AND COMMITMENTS MADE IN THE DEVELOPMENT AGREEMENT ARE BEING ADHERED TO.

Financials

Registration Fee (₹)30000
Project Duration (months)60