ORANJE CASTLE PHASE-3

by SURAJ INFRAVENTURES PVT LTD

Lucknow, Uttar Pradesh · UPRERAPRJ597105/01/2025

Registered

Total units

128

Overview

Registration Date2025-01-29
RERA NumberUPRERAPRJ597105/01/2025
Promoter IDUPRERAPRM724
Proposed Start2025-01-01
Proposed Completion2030-01-09

Location

DistrictLucknow
TehsilSarojini Nagar
VillageSARASWA
LocalityORANJE CASTLE, EMAAR MGF , GOMTI GREENS ,SEC-7
AddressKHASRA- 249, 253, 255, 317, AND 328
StateUttar Pradesh
Map unavailable — no coordinates on file.

Land Details

Project TypeNew
Total Units128
Unit Types4
Blocks5
Floors16

Khasra records (1)

  • KHASRA N0-249, 253, 255, 317, 328· Khasra· 712979

Inventory

Apartments (128 rows)
BlockFloorTypeCountCarpet (m²)BalconyGarage
TOWER-B13 BHK1121.721
TOWER-B13 BHK1115.251
TOWER-B13 BHK1127.171
TOWER-B23 BHK1127.631
TOWER-B23 BHK1116.751
TOWER-B23 BHK1125.021
TOWER-B33 BHK1121.721
TOWER-B33 BHK1115.251
TOWER-B33 BHK1127.171
TOWER-B43 BHK1127.421
TOWER-B43 BHK1116.751
TOWER-B43 BHK1125.021
TOWER-B53 BHK1121.891
TOWER-B53 BHK1149.441
TOWER-B63 BHK1127.421
TOWER-B63 BHK1150.951
TOWER-B73 BHK1121.831
TOWER-B73 BHK1149.441
TOWER-B83 BHK1127.531
TOWER-B83 BHK1146.621
TOWER-B114 BHK1211.691
TOWER-C13 BHK1121.721
TOWER-C13 BHK1115.251
TOWER-C13 BHK1127.171
TOWER-C23 BHK1127.431
TOWER-C23 BHK1116.751
TOWER-C23 BHK1125.41
TOWER-C33 BHK1121.721
TOWER-C33 BHK1115.251
TOWER-C33 BHK1127.171
TOWER-C43 BHK1127.421
TOWER-C43 BHK1116.751
TOWER-C43 BHK1125.41
TOWER-C53 BHK1121.891
TOWER-C53 BHK1115.531
TOWER-C53 BHK1127.241
TOWER-C63 BHK1127.421
TOWER-C63 BHK1116.751
TOWER-C63 BHK1125.41
TOWER-C73 BHK1121.891
TOWER-C73 BHK1115.531
TOWER-C73 BHK1126.931
TOWER-C83 BHK1127.431
TOWER-C83 BHK1116.751
TOWER-C83 BHK1125.41
TOWER-C93 BHK1121.821
TOWER-C93 BHK1150.061
TOWER-C103 BHK1127.851
TOWER-C103 BHK1149.341
TOWER-C154 BHK1229.271
TOWER-D13 BHK1140.81
TOWER-D13 BHK1112.671
TOWER-D13 BHK1124.511
TOWER-D23 BHK1133.981
TOWER-D23 BHK1115.11
TOWER-D33 BHK1140.761
TOWER-D33 BHK1112.671
TOWER-D33 BHK1124.51
TOWER-D43 BHK1134.661
TOWER-D43 BHK1115.11
TOWER-D43 BHK1128.211
TOWER-D53 BHK1140.821
TOWER-D53 BHK1112.571
TOWER-D53 BHK1124.421
TOWER-D63 BHK1134.661
TOWER-D63 BHK1115.11
TOWER-D63 BHK1128.211
TOWER-D73 BHK1140.821
TOWER-D73 BHK1112.571
TOWER-D73 BHK1124.421
TOWER-D83 BHK1134.651
TOWER-D83 BHK1115.11
TOWER-D83 BHK1128.211
TOWER-D94 BHK1224.281
TOWER-D104 BHK1227.471
TOWER-D134 BHK1217.811
TOWER-E13 BHK1108.811
TOWER-E12 BHK1100.411
TOWER-E23 BHK1113.181
TOWER-E22 BHK198.291
TOWER-E33 BHK1108.821
TOWER-E32 BHK1100.41
TOWER-E43 BHK1113.181
TOWER-E42 BHK198.291
TOWER-E53 BHK1108.831
TOWER-E52 BHK1100.41
TOWER-E63 BHK1113.181
TOWER-E62 BHK199.441
TOWER-E73 BHK1108.81
TOWER-E72 BHK199.331
TOWER-E83 BHK1174.051
TOWER-E93 BHK1168.391
TOWER-E103 BHK1174.71
TOWER-F13 BHK1130.11
TOWER-F23 BHK1128.11
TOWER-F33 BHK1130.11
TOWER-F43 BHK1128.11
TOWER-F53 BHK1113.181
TOWER-F52 BHK198.71
TOWER-F63 BHK1108.791
TOWER-F62 BHK198.61
TOWER-F73 BHK1113.181
TOWER-F72 BHK198.71
TOWER-B93 BHK1178.981
TOWER-B94 BHK1184.471
TOWER-C113 BHK1169.521
TOWER-C113 BHK1170.661
TOWER-C123 BHK1177.451
TOWER-C123 BHK1201.551
TOWER-C133 BHK1169.521
TOWER-C133 BHK1170.381
TOWER-C143 BHK1177.471
TOWER-C143 BHK1201.451
TOWER-C164 BHK1293.141
TOWER-D113 BHK1177.261
TOWER-D123 BHK1202.581
TOWER-D123 BHK1153.941
TOWER-D14PENTHOUSE1297.471
TOWER-F83 BHK1188.21
TOWER-F83 BHK1134.351
TOWER-F103 BHK1134.411
TOWER-F103 BHK1188.211
TOWER-F123 BHK1134.431
TOWER-F123 BHK1188.211
TOWER-F143 BHK1134.411
TOWER-F143 BHK1188.211
TOWER-D114 BHK1216.531
TOWER-D23 BHK1128.211

Permits & Approvals

Permit NoGROUPHOUSING/13708/LDA/BP/24-25/2256/24102024
Permit Date2025-01-10
Valid Until2030-01-09
Extendable Until2032-01-09

Documents

Filing documents

  • Proforma of Completion Certificate(Occupancy)
  • Other
  • Details of Encumbrances#New(2024-12-07)
    View
  • Commencement Certificate#New(2024-12-07)
    View
  • Other Plan(If Any)#New(2024-12-07)
    View
  • Proforma of Application Form#New(2024-12-07)
    View
  • Proforma of Allotment Letter#New(2024-12-07)
    View
  • Proforma of Conveyance Deed#New(2024-12-18)
    View
  • Waste Disposal Plan#New(2024-12-27)
    View
  • Water Supply Plan#New(2024-12-27)
    View
  • Electricity Supply Plan#New(2024-12-27)
    View
  • Development Work Plan#New(2024-12-07)
    View
  • Affidavit (Form-B)#New(2025-01-10)
    View
  • CA CERTIFICATE#New(2024-12-20)
    View
  • ARCHITECT CERTIFICATE#New(2024-12-07)
    View
  • ENGINEERS CERTIFICATE#New(2024-12-07)
    View
  • Other#New(2024-12-18)
    View
  • Proforma of Agreement for Sale#New(2024-12-07)
    View

Land documents

  • Sale Deed#14223(2016-09-12)
    13565346480.pdf
    View
  • Sale Deed#1483(2016-09-12)
    13565342308.pdf
    View

Project Team

Architect AddressC-303. RISHI APARTMENT, ALKANANDA, NEW DELHI
Engineer Address1/353, VINAMRA KHAND, GOMTI NAGAR, LUCKNOW

Developer & Contact

Developer

Promoter NameSURAJ INFRAVENTURES PVT LTD
Promoter AddressEMAAR MGF Township, Gomti Greens, Sector - 7, Gomti Nagar Extn. Lucknow 226002 UP IN
Company TypeCompany
Mobile9839022144
Emailaccounts@oranje.co.in
Registered AddressEMAAR MGF Township, Gomti Greens, Sector - 7, Gomti Nagar Extn. Lucknow 226002 UP IN
Contractor Address311-312 SADAR BAZAR , CANTT, LUCKNOW-226002

Bank Accounts

Account Typecollection
Account Number4483002900000136
Account NameSURAJ INFRAVENTURES PVT LTD COLLECTION ACCOUNT ORANJE CASTLE PHASE-3
Bank NamePUNJAB NATIONAL BANK
BranchPUNJAB NATIONAL BANK, LUCKNOW
Branch AddressSPECIAL RETAIL, FINANCE BRANCH GOMTI NAGAR, LUCKNOW
Branch DistrictLucknow
Branch StateSelect
IFSCPUNB0448300
Branch Emailbo4483@pnb.co.in
Account Typeseparate
Account Number4483002900000145
Account NameSURAJ INFRAVENTURES PVT LTD SEPARATE ACCOUNT ORANJE CASTLE PHASE-3
Bank NamePUNJAB NATIONAL BANK
BranchPUNJAB NATIONAL BANK, LUCKNOW
Branch AddressSPECIAL RETAIL, FINANCE BRANCH, GOMTI NAGAR, LUCKNOW
Branch DistrictLucknow
Branch StateUttar Pradesh
IFSCPUNB0448300
Account Typetransaction
Account Number4483002100006006
Account NameSURAJ INFRAVENTURES PVT LTD TRANSACTION ACCOUNT ORANJE CASTLE PHASE-3
Bank NamePUNJAB NATIONAL BANK
BranchPUNJAB NATIONAL BANK, LUCKNOW
Branch AddressSPECIAL RETAIL FINANCE, GOMTI NAGAR, LUCKNOW
Branch DistrictLucknow
Branch StateUttar Pradesh
IFSCPUNB0448300

Development & Facilities

Development works

Demarcation Of PlotsWE HAVE ONE PLOT OF SIZE 7219 SQM HAVING 1 MAIN ENTRANCE AND 1 EXIT GATE FROM THE 45 M WIDE FRONT ROAD.
Boundary Wall2M HIGH AND 230 MM THICK RCC/MS 1 SECTION WORK WHICH GIVE A BEAUTIFUL ICONIC DESIGN BOUNDARY WALL AND WILL BE DONE ON BOTH SIDE OF THE BOUNDARY WALL AFTER THAT TWO COAT OF PAINTS WIL BE COATED.
Road WorkCONCRETE /APEX ROAD WILL BE MADE AT THE SITE , THE BASE OF THE ROAD WILL BE FILLED BY RED MURUM , AFTER THAT 2 LAYER OF AGREEGATE WILL BE LAYED TO MAKE SURE THAT THET THE TOAD FROM THE MAIN ENTRANCE / EXIT GATE WE HAVE 100MM THICK 6MTR WIDE RCC ROAD THROUGH OUT THE PROJECT.
FootpathsWE WOULD PROVIDE FOOTHPATH THROUGH BRICK TILE. ALL FOOTHPATH IN THE PROJECT WILL BE IN COMBINATION SIZE THICNESS OF 65MM , 80MM LAID OVER 150MM.
Water Supply Including Drinking Water FacilitiesWE WILL PROVIDE PUMPS FOR THE REQUIREMENT OF BLOCKS THROUGH PIPELINES AND PUMPED TO OVER HEAD WATER TANK . THE SUPPLY OF WATER TO INDIVIDUAL FLATS SHALL BE FROM THE SAID OVER HEAD WATER TANK..
Sewer SystemMODULAR SEWERAGE SYSTEM SHALL BE PROVIDED. ALL SEWERAGE WATER SHALL BE GO TO THE STP AND AFTER TREATMENT RE-USE IN FLUSH AND GARDEN. OVERFLOW FROM THE STP SHALL BE CONNECT WITH THE MUNICIPAL SEWERAGE SYSTEM WHEN COME INTO FORCE.
DrainSTORM WATER SHALL BE PROVIDED. STORM WATER FROM TERACES, ROADS AND OTHER LANDSCAPE AREA SHALL BE CONNECT TO THE STORM WATER DRAIN CHANNEL AND GO TO THE RAIN WATER HARVESTING PIT FOR RECHARGE THE GROUND WATER AND OVERFLOW SHALL BE CONNECT WITH MUNICIPAL DRAIN LINE.
ParksWE WILL PROVIDE GREEN AREA WITH THE DIFFRENT ACTIVITIES AND WILL HAVE GAMING FACILITIS FOR KIDS
Tree PlantingWE WILL PROVIDE MANY TYPE OF TREES ALL ALONG THE BOUNDARY WALL AND GREEN AREA.
Design For Electric Supply Including Street LightingWE WILL DESIGN AND IMPLEMENT THE SYSTEM AS PER LOCAL ELECTRICITY BOARD AND WILL CONSIDER CENTRALIZED TRANSFORMER, HT PANEL, LT PANEL, FEEDER PILLER AND DG BACK FOR COMMON SERVICE LIKE EXTERNAL LIGHTING, FOUNDATION, STP, PUMP ROOM ETC.
Community BuildingsWE WILL PROVIDE COMMUNITY HALL AND CLUB
Treatment And Disposal System Of Sewage And Sullage WaterMODULAR SEWERAGE SYSTEM SHALL BE PROVIDED. ALL SEWERAGE WATER SHALL BE GO TO THE STP AND AFTER TREATMENT RE-USE IN FLLUSH AND GARDEN. OVERFLOW FROM THE STP SHALL BE CONNECT WITH THE MUNICIPAL SEWERAGE SYSTEM. WHEN COME INTO FORCE.
Solid Waste Management And Disposal SystemSOLID WASTE TO BE COLLECTED FROM INDIVIDUAL FLATS AND STORED IN GARBAGE ROOM, RECYCLABLE SHALL BE PROCESSED IN THE COMPOSE MACHINE TO MAKE.
Water Conservation SystemWE WILL SUGGEST TO INDIVIDUAL TO USE LOW FLOW FIXTURES AS WELL DUAL FLUSH CISTERN AND RAW WATER HARVESTING SYSTEM WILL BE PROVIDED TO REDUCE THE WATER CONSUMTION AND IMPROVE THE GROUND WATER LVEL.
Energy Management System Including Use Of Renewable EnergyWE WILL USE LED LIGHT FITTING IN INTERNAL AREA AS WELL AS SOLAR LIGHTS. IN PUMP ROOM ALSO ALL THE EQUIPMENT SHALL HAVE ENERGY EFFICIENT MOTOR.
Fire Protection And Fire Safety SystemFIRE FIGHTING SYSTEM, FA SYSTEM AS WILL BE PROVIDED LOCAL AUTHORITIES REQUIREMENT.
Social Infrastructure And Other Public Amenities Including Public Health ServicesPROVISION PROVIDED.
Emergency Evacuation ServicesWE WILL HAVE FIRE STAIRCASES WHICH WILL BE PROVIDED WITH EMERGENCY EXIT DOORS.
Other Miscellaneous WorkN/S

Financials

Registration Fee (₹)41500
Project Duration (months)61