Sardar Vallabh Bhai Patel Awasiya Yojana
by Lucknow Development Authority
Lucknow, Uttar Pradesh · UPRERAPRJ326544/08/2025
Total units
72
Overview
Registration Date2025-08-23
RERA NumberUPRERAPRJ326544/08/2025
Promoter IDUPRERAPRM10102
Proposed Start2025-08-01
Proposed Completion2029-12-12
Location
DistrictLucknow
TehsilLucknow
Villagejiyamau
AddressKhasra No.93
StateUttar Pradesh
Map unavailable — no coordinates on file.
Land Details
Project TypeNew
Total Units72
Unit Types1
Blocks2
Floors4
Khasra records (1)
- Letter· Khasra· 232123 m²
Inventory
Apartments (8 rows)
| Block | Floor | Type | Count | Carpet (m²) | Balcony | Garage |
|---|---|---|---|---|---|---|
| Block-1 | GF | 1 BHK | 14 | 21.101 | 1 | — |
| Block-1 | 1 | 1 BHK | 14 | 21.101 | 1 | — |
| Block-1 | 2 | 1 BHK | 14 | 21.101 | 1 | — |
| Block-1 | 3 | 1 BHK | 14 | 21.101 | 1 | — |
| Block-2 | GF | 1 BHK | 4 | 21.101 | 1 | — |
| Block-2 | 1 | 1 BHK | 4 | 21.101 | 1 | — |
| Block-2 | 2 | 1 BHK | 4 | 21.101 | 1 | — |
| Block-2 | 3 | 1 BHK | 4 | 21.101 | 1 | — |
Permits & Approvals
Permit No440/APA/2024
Permit Date2024-12-13
Valid Until2029-12-12
Extendable Until2032-12-12
Documents
Filing documents
- Details of Encumbrances
- Other Plan(If Any)
- Proforma of Completion Certificate(Occupancy)
- Development Work Plan
- Other
- Details of Encumbrances#New(2025-08-13)View
- Commencement Certificate#New(2025-07-16)View
- Other Plan(If Any)#New(2025-08-13)View
- Proforma of Application Form#New(2025-07-16)View
- Proforma of Allotment Letter#New(2025-07-16)View
- Proforma of Conveyance Deed#New(2025-07-16)View
- Waste Disposal Plan#New(2025-08-19)View
- Water Supply Plan#New(2025-08-20)View
- Electricity Supply Plan#New(2025-08-20)View
- Development Work Plan#New(2025-08-05)View
- Affidavit (Form-B)#New(2025-08-12)View
- CA CERTIFICATE#New(2025-07-16)View
- ARCHITECT CERTIFICATE#New(2025-07-16)View
- ENGINEERS CERTIFICATE#New(2025-07-17)View
- Proforma of Agreement for Sale#New(2025-07-16)View
Land documents
- Extract of Khatauni#Letter(1900-01-01)View16233955241.pdf
Project Team
Architect AddressPradhikaran Bhawan Vipin Khand Gomti Nagar Lucknow
Engineer AddressPradhikaran Bhawan Vipin Khand Gomti Nagar Lucknow.
Developer & Contact
Developer
Promoter NameLucknow Development Authority
Promoter AddressLucknow Development Authority, Vipin Khand, Gomti Nagar, Lucknow
Company TypeCompetent authority
Mobile9918005512
Emailvicechairmanlda@gmail.com
Registered AddressLucknow Development Authority, Vipin Khand, Gomti Nagar, Lucknow
Contractor AddressPradhikaran Bhawan vipin Khand Gomti Nagar Lucknow
Development & Facilities
Development works
Demarcation Of PlotsPlot is already demarcated and the construction work is in progress with in the boundary.
Boundary WallPlot is already demarcated and the construction work is in progress with in the boundary.
Road Work5 meter wide road Network ( Wrt to NBC 2016 and Byelaws 2025) is proposed around the towers. The finishing on the road network is Cement Concrete.
FootpathsFootpath along the Setback are proposed be finished with interlocking tiles.
Water Supply Including Drinking Water FacilitiesA borewell in proposed in the open setback green area and the supply lines are directly connected to the OHTs on the tower.
Sewer SystemA 300 mm dia NP2 types pipes are proposed to be laid and finally connected to the main Municipal sewer line along the road.
DrainStorm water system will be provided which will be connected to the Municipal drain/Trunk line as per specified plan.
ParksA small green patch in the setback is provided.
Tree PlantingA few Trees will be planted in the setback as per sanctioned plan.
Design For Electric Supply Including Street LightingA Centralized transformer, HT panel, LT panel, services like external lighting. is proposed as per sanctioned plan. for the L.T., L.V., and H.T. lines
Community BuildingsThere is no community building proposed in our project.
Treatment And Disposal System Of Sewage And Sullage WaterSewage System is to be laid and finally connected to the Main line.
Solid Waste Management And Disposal SystemFor Waste management and garbage collection chambers are proposed as per layout. After completing the project, it will be handed over to the local municipal corporation.
Water Conservation SystemA well-designed rainwater harvesting system shall be provided.
Energy Management System Including Use Of Renewable EnergyLED lights proposals for street lights.
Fire Protection And Fire Safety SystemThe Building Height is less than 15 Meters.
Social Infrastructure And Other Public Amenities Including Public Health ServicesNot applicable
Emergency Evacuation ServicesNot applicable
Other Miscellaneous WorkNot applicable
Financials
Registration Fee (₹)17000
Project Duration (months)53