TRYAMBAKAM DEVELOPERS

by TRYAMBAKAM DEVELOPERS

Lucknow, Uttar Pradesh · UPRERAPRJ697106

Registered

Overview

Registration Date2023-03-21
RERA NumberUPRERAPRJ697106
Promoter IDUPRERAPRM215410
Proposed Start2022-12-26
Proposed Completion2027-12-25

Location

DistrictLucknow
TehsilBakshi Ka Talab**
StateUttar Pradesh
Map unavailable — no coordinates on file.

Land Details

Project TypeNew
Plots27

Khasra records (1)

  • 1360/1105, 1101(P), 1110(P), 1102(P), 1103(P) , 1112(P)· Khasra· 768341

Inventory

Plots

TypeSize rangeCount
Plot150 to 200 sqm21
Plot200 to 250 sqm2
Plot250 to 500 sqm4

Permits & Approvals

Permit NoPLOTTED RESI DEVELOPEMENT/PLOTTED HOUSING/03340/LDA/LD/21-22/0791/21102021
Permit Date2022-12-26
Valid Until2027-12-25
Extendable Until2027-12-25

Documents

Filing documents

  • Details of Encumbrances
  • Other Plan(If Any)
  • Other Plan(If Any)
  • Proforma of Allotment Letter
  • Proforma of Allotment Letter
  • Proforma of Conveyance Deed
  • Proforma of Conveyance Deed
  • Proforma of Completion Certificate(Occupancy)
  • Waste Disposal Plan
  • Affidavit (Form-B)
  • Affidavit (Form-B)
  • CA CERTIFICATE
  • CA CERTIFICATE
  • ARCHITECT CERTIFICATE
  • General body resolution for AoA (if Authorized Entity is AoA)
  • Notarized Affidavit for completion of balance development work
  • Details of Encumbrances#New(2023-02-22)
    View
  • Commencement Certificate#New(2023-01-23)
    View
  • Other Plan(If Any)#New(2023-03-15)
    View
  • Proforma of Application Form#New(2023-02-23)
    View
  • Proforma of Allotment Letter#New(2023-03-14)
    View
  • Proforma of Conveyance Deed#New(2023-03-14)
    View
  • Waste Disposal Plan#New(2023-03-14)
    View
  • Water Supply Plan#New(2023-01-23)
    View
  • Electricity Supply Plan#New(2023-01-23)
    View
  • Development Work Plan#New(2023-01-23)
    View
  • Affidavit (Form-B)#New(2023-03-17)
    View
  • CA CERTIFICATE#New(2023-03-14)
    View
  • ARCHITECT CERTIFICATE#New(2023-02-20)
    View
  • ENGINEERS CERTIFICATE#New(2023-01-23)
    View
  • Other#New(2023-01-23)
    View

Land documents

  • Lease Deed#IN-UP16770967438287T(2021-07-27)
    6683819426Developer LEASE Agreements-min.pdf
    View

Project Team

Architect Address11 GAYATRI SHAKTI PEETH PATEL PURAM GOMTI NAGAR 226010
Engineer AddressNA

Developer & Contact

Developer

Promoter NameTRYAMBAKAM DEVELOPERS
Promoter Address11 A BRAHMA NAGAR SITAPUR ROAD NIRALA NAGAR LUCKNOW 226020
Company TypePartnership Firm
Mobile8005211668
EmailTRYAMBAKAM.01@GMAIL.COM
Registered Address11 A BRAHMA NAGAR SITAPUR ROAD NIRALA NAGAR LUCKNOW 226020
Contractor AddressNA

Bank Accounts

Account Typecollection
Account Number1007102100000277
Account NameTRYAMBAKAM DEVELOPERS COLLECTION ACCOUNT FOR TRYAMBAKAM DEVELOPERS
Bank NamePUNJAB NATIONAL BANK
BranchSAHARA ESTATE JANKIPURAM
Branch AddressSTATE PLAZA SAHARA PLAZA JANKIPURAM LUCKNOW
Branch DistrictLucknow
Branch StateUttar Pradesh
IFSCPUNB0100710
Account Typeseparate
Account Number1007102100000301
Account NameTRYAMBAKAM DEVELOPERS SEPRATE ACCOUNT FOR TRYAMBAKAM DEVELOPERS
Bank NamePUNJAB NATIONAL BANK
BranchSTATE PLAZA SAHARA ESTATE
Branch AddressSTATE PLAZA SAHARA PLAZA JANKIPURAM
Branch DistrictLucknow
Branch StateUttar Pradesh
IFSCPUNB0100710
Account Typetransaction
Account Number1007102100000286
Account NameTRYAMBAKAM DEVELOPERS TRANSACTION ACCOUNT FOR TRYAMBAKAM DEVELOPERS
Bank NamePUNJAB NATIONAL BANK
BranchSAHARA STATE JANKIPURAM
Branch AddressSTATE PLAZA SAHARA PLAZA JANKIPURAM LUCKNOW
Branch DistrictLucknow
Branch StateUttar Pradesh
IFSCPUNB0100710

Development & Facilities

Development works

Demarcation Of PlotsDEMARCATIONS OF PLOTS WILL BE DONE BY BRICKS AND BY STEEL WIRE AS PER THE REQUIREMENT OF BUYER
Boundary WallBOUNDRY WALL WILL BE CONSTRUCTED BY USING BRICKS WALL WHICH WILL TAKES 3-4 MONTH TO COMPLETE
Road WorkROAD CONSTRUCTION WILL BE DONE BY LAYING OF C.C. INTERLOCKING TILES WHICH MAY TAKE APPROX 5-6 MONTH TO COMPLETE
FootpathsFOOTHPATH WORKS COMPLETES SIDE BY SIDE THE ROAD CONSTRUCTION WORK BY USING INTERLOCKING TILES OF RED COLOUR
Water Supply Including Drinking Water FacilitiesTUBEWELL WILL BE CONSTRUCTED (PLINTH AREA RATE 5.4.2) . IT MAY TAKE 1-2 MONTH TO COMPLETE
Sewer SystemSEWER LINE WORK WILL BE STARTED BEFORE ROAD CONSTRUCTION WORK .
DrainCOMPLETE DRAIN PLAN LAYOUT IS READY AND IT WILL BE CONSTRUCTED SIDE BY SIDE BY OTHER WORK.LAYOUT UPLOADED
ParksNUMBER OF PARK -01
Tree Plantingtikona plant and EUCALYPTUS PLANT WILL BE PLANTED AT BOUNDRY WALL OF THE PROJECT WHICH MAY TAKE 2-3 MONTH TO COMPLETE
Design For Electric Supply Including Street LightingRoad side pole light and We will also establish underground supply of electricity and it may take 1 year to complete as it depends upon completion of other work too
Community BuildingsNA (ONLY PLOT DEVELOPEMENT)
Treatment And Disposal System Of Sewage And Sullage WaterNA
Solid Waste Management And Disposal SystemNA (ONLY PLOT DEVELOPEMENT)
Water Conservation SystemNA
Energy Management System Including Use Of Renewable EnergyNA
Fire Protection And Fire Safety SystemNA
Social Infrastructure And Other Public Amenities Including Public Health ServicesNA
Emergency Evacuation ServicesNA
Other Miscellaneous WorkREPAIR AND MAINTENANCE WORK (ROUTINE WEAR AND TEAR) MAINTENANCE OF RAOD PARKS ETC

Financials

Registration Fee (₹)51000
Project Duration (months)60