VEDANSHA GREENS-5

by SWEKRETI REALTORS LLP

Moradabad, Uttar Pradesh · UPRERAPRJ449605/04/2026

Registered

Overview

Registration Date2026-04-27
RERA NumberUPRERAPRJ449605/04/2026
Promoter IDUPRERAPRM321484
Proposed Start2025-12-01
Proposed Completion2030-08-02

Location

DistrictMoradabad
TehsilMoradabad
VillageVILLAGE HARTHALA EHATMALI TEHSIL AND DISTRICT MORADABAD-244001
AddressKHASRA NO. 1344 AND 1345 VILLAGE HARTHALA EHATMALI TEHSIL AND DISTRICT MORADABAD-244001
StateUttar Pradesh
Map unavailable — no coordinates on file.

Land Details

Project TypeNew
Plots29

Khasra records (2)

  • 1344· Khasra· 244283
  • 1345· Khasra· 19682

Inventory

Plots

TypeSize rangeCount
PlotAbove 500 sqm5
Plot250 to 500 sqm24

Permits & Approvals

Permit NoPlotted Resi development / Plotted Housing/03984/MBDA/LD/25-26/0633/07032026
Permit Date2026-03-07
Valid Until2031-03-06
Extendable Until2031-03-06

Documents

Filing documents

  • Details of Encumbrances
  • Commencement Certificate
  • Other Plan(If Any)
  • Proforma of Conveyance Deed
  • Proforma of Completion Certificate(Occupancy)
  • Waste Disposal Plan
  • Waste Disposal Plan
  • Water Supply Plan
  • Water Supply Plan
  • Electricity Supply Plan
  • Electricity Supply Plan
  • Development Work Plan
  • Development Work Plan
  • ARCHITECT CERTIFICATE
  • ARCHITECT CERTIFICATE
  • ARCHITECT CERTIFICATE
  • ARCHITECT CERTIFICATE
  • ENGINEERS CERTIFICATE
  • General body resolution for AoA (if Authorized Entity is AoA)
  • Notarized Affidavit for completion of balance development work
  • Other
  • Proforma of Agreement for Sale
  • Proforma of Agreement for Sale
  • Details of Encumbrances#New(2026-01-09)
    View
  • Commencement Certificate#New(2026-03-17)
    View
  • Proforma of Application Form#New(2026-01-03)
    View
  • Proforma of Allotment Letter#New(2026-01-03)
    View
  • Proforma of Conveyance Deed#New(2026-03-17)
    View
  • Waste Disposal Plan#New(2026-03-17)
    View
  • Water Supply Plan#New(2026-03-17)
    View
  • Electricity Supply Plan#New(2026-03-17)
    View
  • Development Work Plan#New(2026-03-17)
    View
  • Affidavit (Form-B)#New(2026-01-09)
    View
  • CA CERTIFICATE#New(2026-01-09)
    View
  • ARCHITECT CERTIFICATE#New(2026-04-09)
    View
  • ENGINEERS CERTIFICATE#New(2026-03-19)
    View
  • Other#New(2026-02-05)
    View
  • Proforma of Agreement for Sale#New(2026-03-17)
    View

Land documents

  • Registry Document#3641(2024-03-13)
    18714235511.pdf
    View
  • Registry Document#4385(2024-03-30)
    18714233544.pdf
    View
  • Registry Document#5235(2024-04-22)
    18714233437.pdf
    View
  • Registry Document#5234(2024-04-22)
    18714237042.pdf
    View
  • Extract of Khatauni#1425-1430(1900-01-01)
    18714239418.pdf
    View
  • Extract of Khatauni#1425-1430(1900-01-01)
    18714236548.pdf
    View
  • Extract of Khatauni#CONSORTIUM AGREEMENT(2026-03-19)
    18714239450.pdf
    View

Project Team

Architect AddressPilli Kothi, Moradabad-244001
Engineer Address389, Ground Floor, IP Colony, Sector-30/33 Faridabad -121003- Haryana

Developer & Contact

Developer

Promoter NameSWEKRETI REALTORS LLP
Promoter AddressBASEMENT, HC-48, RAM GANGA VIHAR, PHASE II, MORADABAD UTTAR PRADESH, INDIA, 244001
Company TypeLimited Liability Partnership (LLP)
Mobile9258316347
Emailswekretirealtorsllp74@gmail.com
Registered AddressBASEMENT, HC-48, RAM GANGA VIHAR, PHASE II, MORADABAD UTTAR PRADESH, INDIA, 244001
Contractor Address6, Avas Vikas Market, Pilli Khoti, Moradabad-244001

Bank Accounts

Account Typecollection
Account Number99999927999279
Account NameSWEKRETI REALTORS LLP COLLECTION A/C FOR VEDANSHA GREENS-5
Bank NameHDFC BANK
BranchMANSAROVAR COLONY MORADABAD
Branch AddressGANDHI COMPLEX , DELHI ROAD,MORADABAD-244001
Branch DistrictMoradabad
Branch StateUttar Pradesh
IFSCHDFC0007265
Branch Emailpriya.johri@hdfcbank.com
Account Typeseparate
Account Number99999837098370
Account NameSWEKRETI REALTORS LLP SEPARATE BANK A/C FOR VEDANSHA GREENS-5
Bank NameHDFC BANK
BranchMANSAROVAR COLONY, MORADABAD
Branch AddressGANDHI COMPLEX,DELHI ROAD, MORADABAD-244001
Branch DistrictMoradabad
Branch StateUttar Pradesh
IFSCHDFC0007265
Account Typetransaction
Account Number99999412294122
Account NameSWEKRETI REALTORS LLP RERA TRANSACTION A/C FOR VEDANSHA GREENS-5
Bank NameHDFC BANK
BranchMANSAROVAR COLONY, MORADABAD
Branch AddressGANDHI COMPLEX, DELHI ROAD, MORADABAD-244001
Branch DistrictMoradabad
Branch StateUttar Pradesh
IFSCHDFC0007265

Development & Facilities

Development works

Demarcation Of PlotsDemarcation of plots will be done as per layout. The total numbers of plots 29 NOS.
Boundary WallThe boundary wall is in 3 Mt. high that is built on 230 mm thick brick wall is first class brick work is a ratio of 1;6 mix, with providing column is every 4 Mt., Expansion joint and beam for high durability damp proof course layer will also laid for moisture resistant purpose.
Road WorkInternal road is 12 Mt., 9Mt. and 7.50 Mt. wide . All Road are RCC with proper compaction 8 inch boulder will be use, Ready mixed concrete will be used which is manufactured is fully automatic batching plant and designed upto 100 MT load capacity.
FootpathsA 1.5 m wide footpath runs all along the fence outside a park, foothpath provide an excellent opportunity for exercise as well an movement. Fothpath can be used as decorative cycle paths, running paths and many others. As such these foothpath need to be designed with access in mind. They must also be durable safe and easy to maintain.
Water Supply Including Drinking Water FacilitiesWater supply will be provided by the developer through overhead wate tank. All water supply pipes elbows, tee, socket etc. Will be of uniq make ISI marked.
Sewer SystemSTP 25 KLD Capacity ( Sewerage Treatment plant ) is proposed by developer with MBBR technology with clog pump, irrigation pump etc.
DrainProviding and laying cast in site RCC drain , storm water lines will be provided by the developers along with roads. All drain pipes and rain water pipes to be make 6kg pressure pipe ISI marked and all PVC fitting to be of ISI marked. Gully Traps and main as per detail drawing.
ParksPark are the gathering spaces for the entire neighborhood. As a result more pepole spend their time in the park. Cutgrass and manicured trees give attention the pepole. Whilechildrens play area is also provided in the park. Whare all the children are of the society will enjoy and play outdoor games. It also includes picnic tables, benches, walkways, recreational trails, shade structures and lighting.
Tree PlantingPlantation will be done by the developers as per layout. Tree planting is cost- effective, thus making it simpler to achieve the goel of making the earth a safer place by making it free from pollution. The effects of climate change can also be controlled by increading the rate of tree plantation.
Design For Electric Supply Including Street LightingStreet lightning lines will be laid along the road. The distance between street lightning will be 15 to 20 Mts. Electrical substation will also proposed by developers. Three (3) Trasnformers of 250 KVA Capacity each shall be provide. Wires, Switch socket crabtree or anchor roma make, MCB-ISI make, Conduilt ISI marked. D.B Box ISI marked, Gang box, Fan box, Light box etc. As per ISI norms.
Community BuildingsNA
Treatment And Disposal System Of Sewage And Sullage WaterSTP system proposed by the developers for treatment and disposal system of sewage and sullage water. Sewer lines are around 15-300 mm.
Solid Waste Management And Disposal SystemSolid waste management and disposal system will be done by the developers. All drain pipes and rain water pipes to be make 6kg pressure pipe ISI marked. All PVC fitting to be of ISI marked. Gully traps and main hole as per detail drwaing.
Water Conservation SystemRain water harvesting tank will be constructed by the developer. It is used to transport the harvested water from the catchment to the recharge zone. It improves the quality and quantity of ground water. It also reduces soil erosion, stromwater runoff, flooding and pollution of surface water with fertilizers, pesticides, metals and other sediments. It maintain is very important to maintain water level.
Energy Management System Including Use Of Renewable EnergyNA
Fire Protection And Fire Safety SystemNA
Social Infrastructure And Other Public Amenities Including Public Health ServicesNA
Emergency Evacuation ServicesNA
Other Miscellaneous WorkTo be done as per approved layout

Financials

Registration Fee (₹)116000
Project Duration (months)57